Project: West Marine View Drive Utilities <br /> Change Order No. 1 <br /> Change Order Effective Date: May 29,2019 <br /> CONTRACTOR • <br /> By 4 Date: 5 /Lei f �j <br /> Officer <br /> Exhibit A—Description of Changed Work <br /> Change Order#1 modifies four(4) existing bid items as follows: <br /> Bid Item #12—Planing Bituminous Pavement. Modify bid item#12 titled,Planing Bituminous <br /> Pavement,by deleting all work under this bid item,resulting in a$4,110.75 reduction in the contract <br /> price. <br /> Bid Item#17—Crushed Surfacing Base Course. Modify bid item#17 titled, Crushed Surfacing <br /> Base Course, by adding 743.79 tons of Crushed Surfacing Top Course at the unit price of$17.25/ton, <br /> resulting in a$12,830.38 addition to the contract price. <br /> Bid Item#18—Control Density Fill. Modify bid item#18 titled, Control Density Fill,by deleting 94 <br /> cubic yards of Control Density Fill at the unit price of$115.00/CY,resulting in a$10,810.00 reduction <br /> in the contract price. <br /> Bid Item #44—Pavement Markings. Modify bid item#44 titled,Pavement Markings, by deleting all <br /> work under this bid item,resulting in a$4,575.00 reduction in the contract price. <br /> The result of making modifications to the four(4) aforementioned bid items is a$6,665.37 reduction to <br /> the contract bid price. <br /> JUSTIFICATION: <br /> Bid Item #12—Planing Bituminous Pavement& <br /> Bid Item#44—Pavement Markings <br /> Work under the above two bid items is being deleted due to the close proximity of the work being <br /> performed on the Grand Avenue Park Bridge project(GAPB),as Interwest Construction crews are <br /> occupying some of the same space to construct the new pedestrian bridge. Once work is nearing <br /> completion on GAPB project, if work is needed on travel lanes of West Marine View Drive under <br /> these two bid items, it will be performed on the Contract for GAPB project. <br /> Page 3 of 4 <br />