IX. IMPLEMENTATION SCHEDULE <br /> Select contractor December 2017 <br /> All financing committed December 2017 <br /> Complete drawings and specs February 2018 <br /> WSHFC Credit Reservation & Carry-Over Allocation Contract August 28, 2017 <br /> Financing Closing May 1, 2018, 2018 <br /> Building Permit issued April 20, 2018 <br /> Notice to Proceed May 7, 2018 <br /> Begin construction May 7, 2018 <br /> 50% construction completion December 2018 <br /> Certificate of substantial completion issued August 2019 <br /> Stabilized Occupancy October 2019 <br /> Project Close-out April 2020 <br /> Exhibit A <br /> Housing Hope Properties <br /> Page 8 of 7 <br />