Laserfiche WebLink
Design Milestone Milestone Deadline <br /> Task A: 60%plans and specifications for transmission line 8 weeks after ILA <br /> work are available for comment <br /> Task B: Comments due on 60%plans and specifications for 2 weeks after 60%submittal <br /> transmission line work (Task A) <br /> Task C: 90%plans and specifications for transmission line 5 weeks after 60%submittal <br /> work are available for comment (Task B) <br /> Task D: Comments on 90%plans and specifications for 3 weeks after 90%submittal <br /> transmission line work (Task C) <br /> Task E: Everett provides to Lake Stevens approval of final 10 weeks after 90% <br /> transmission line plans and specifications for inclusion in Lake submittal (Task C) <br /> Stevens' 91st Ave Project bid package <br /> All portions of the table above may be adjusted by written agreement between the Directors of <br /> Public Works of Everett and Lake Stevens or their designees. For this Agreement, the final plans <br /> and specifications for transmission line work approved by Everett are the "Final Transmission <br /> Line Project Plans and Specifications." For this Agreement,the term"Transmission Line Work" <br /> refers to all construction, materials, labor and other activities and items necessary to complete all <br /> work and improvements in accordance with the Final Transmission Line Project Plans and <br /> Specifications. <br /> 3. Everett Approval of Final Plans. Lake Stevens will provide the final project plans <br /> and specifications for the 91st Ave Project and the Transmission Line Work to Everett at least 30 <br /> days before the 91st Ave Project and Transmission Line Work are advertised for bid. Lake Stevens <br /> will not start construction unless Everett's Public Works Director or his designee has approved in <br /> writing such project plans and specifications. This approval will not be withheld so long as such <br /> plans and specifications include the Final Transmission Line Project Plans and Specifications and <br /> are in accordance with this Agreement and the 91st Ave Use Permit. <br /> B. Permitting. <br /> 1. Lake Stevens will be the lead agency responsible for review and approval of <br /> permitting including but not limited to SEPA review, land disturbance and civil construction <br /> drawings in coordination with affected agencies and interested parties <br /> 2. Lake Stevens will apply for and obtain any necessary permits to allow for <br /> construction of the 91st Ave Project and the Transmission Line Work. Everett will fully cooperate <br /> with Lake Stevens in obtaining such permits. <br /> C. Procurement. <br /> 1. Construction Contract Award (Single Contract). If Lake Stevens determines that <br /> the 91st Ave Project and Transmission Line Work will be awarded in a single contract, then Lake <br /> 3 <br />