ARTICLE 8. EAST CLEARWELL ROOF WATER-TIGHTNESS TESTING <br /> 8.1 Roof <br /> 8.1.1 Test Plan <br /> Design-Builder shall submit a Testing Plan to the Owner's Representative that sets forth detailed <br /> step-by-step descriptions of the procedures that will be used by the Design-Builder to demonstrate <br /> that the installed roof system is water tight.Test plan shall be submitted at least 30 days prior to <br /> Initiating the tests.At a minimum,test plan shall address: <br /> • Methods for sealing vents prior to the test <br /> • Methods for applying water to the roof, including access hatches and connection points to <br /> the existing clearwell,to simulate intense precipitation conditions typical of the area (i.e.a <br /> 50-year event) <br /> • Characteristics of rainfall event to be simulated <br /> • Criteria for repair and re-testing <br /> • Notification of City and testing schedule <br /> The test plan shall be reviewed and approved by the Owner's Representative prior to conducting the <br /> test. <br /> 8.1.2 Conduct of Tests <br /> Design-Builder shall not initiate tests until clearwell interiors are dry.Testing shall be satisfactorily <br /> completed,as agreed to by Owner's Representative, prior to initiating East Clearwell water-tightness <br /> testing. <br /> Design-Builder shall notify Owner's Representative of each test, and shall allow Owner's <br /> Representative access to the clearwell interior during testing. Design-Builder shall video document <br /> the results of the tests. <br /> If testing results in visible leaks through the roof, including access hatches and connection points, <br /> Design-Builder shall investigate and repair the source of the leaks and re-test until satisfactory. <br /> results are obtained.A visible leak is defined as an observed stream or ongoing drip of water into the <br /> interior of the clearwell. <br /> Nothing in this Article shall waive Design-Builder's warranty obligations under the Contract <br /> Documents. <br /> 8.2 Clearwell Leakage <br /> 8.2.2 Test Plan <br /> After construction is complete and prior to disinfection, Design Builder shall conduct leakage testing <br /> consistent with the methods used by the City,described in Article 4,Section 4.6.4. <br /> If testing results reveal leakage greater than 1,000 gpd, Design-Builder shall investigate and repair <br /> the source of the leaks and re-test until satisfactory. <br /> City of Everett January 29,2020 <br /> Water Filtration Plant East Clearwell Roof Replacement DB Project Supplementary Conditions Page 18 <br />