Laserfiche WebLink
111 <br /> 1 Contractor, take whatever steps are necessary to correct those deficiencies pursuant to <br /> 2 Section 1-05.7. <br /> 3 The Contractor will not be allowed an extension of contract time because of a delay in the <br /> 4 performance of the work attributable to the exercise of the Engineer's right hereunder. <br /> 5 <br /> 6 Upon correction of all deficiencies, the Engineer will notify the Contractor and the Contracting <br /> 7 Agency, in writing, of the date upon which the work was considered physically complete. That <br /> 8 date shall constitute the Physical Completion Date of the contract, but shall not imply I <br /> 9 acceptance of the work or that all the obligations of the Contractor under the contract have <br /> 10 been fulfilled. <br /> 11 I <br /> 12 1-05.11(3) Operational Testing <br /> 13 <br /> 14 It is the intent of the Contracting Agency to have at the Physical Completion Date a <br /> 15 complete and operable system. Therefore when the work involves the installation of <br /> 16 machinery or other mechanical equipment; street lighting, electrical distribution or signal <br /> 17 systems; irrigation systems; buildings; or other similar work it may be desirable for the I <br /> 18 Engineer to have the Contractor operate and test the work for a period of time after final <br /> 19 inspection but prior to the physical completion date. Whenever items of work are listed in the <br /> 20 Contract Provisions for operational testing they shall be fully tested under operating <br /> 21 conditions for the time period specified to ensure their acceptability prior to the Physical <br /> 22 Completion Date. During and following the test period, the Contractor shall correct any items <br /> 23 of workmanship, materials, or equipment which prove faulty, or that are not in first class <br /> 24 operating condition. Equipment, electrical controls, meters, or other devices and equipment <br /> 25 to be tested during this period shall be tested under the observation of the Engineer, so that <br /> 26 the Engineer may determine their suitability for the purpose for which they were installed. <br /> 27 The Physical Completion Date cannot be established until testing and corrections have been I <br /> 28 completed to the satisfaction of the Engineer. <br /> 29 <br /> 30 The costs for power, gas, labor, material, supplies, and everything else needed to <br /> 31 successfully complete operational testing, shall be included in the unit contract prices <br /> 32 related to the system being tested, unless specifically set forth otherwise in the proposal. <br /> 33 I <br /> 34 Operational and test periods, when required by the Engineer, shall not affect a manufacturer's <br /> 35 guaranties or warranties furnished under the terms of the contract. <br /> 36 <br /> 37I38 1-05.13.RTF <br /> 39 1-05.13 Superintendents, Labor and Equipment of Contractor <br /> 40 (August 14, 2013 APWA GSP) I <br /> 41 <br /> 42 Delete the sixth and seventh paragraphs of this section. <br /> 43 <br /> 44 1-05.14.GR1 <br /> 45 Cooperation With Other Contractors <br /> 46 <br /> 47 <br /> 48 (March 13, 1995) <br /> 49 Other Contracts Or Other Work I <br /> 50 It is anticipated that the following work adjacent to or within the limits of this project will be <br /> 51 performed by others during the course of this project and will require coordination of the work: <br /> 53 I <br /> 53 **A. <br /> 2020 PAVEMENT MAINTENANCE OVERLAY PAGE 14 OF 79 SPECIAL PROVISIONS <br /> WORK ORDER 3727 FEBRUARY 20,2020 <br />