November 11, 2016 <br /> HWA Project No. 2014-117-21 <br /> 4.6 SIGNAL POLE FOUNDATIONS <br /> We understand six new cantilever traffic signals are proposed for this project. We understand all <br /> signals will consist of a cantilever signal pole conforming to the WSDOT Standard Plans. Three <br /> cantilever traffic signals are proposed near the eastern transit entrance, to facilitate access from <br /> the transit facility to 75th Street SW, and three cantilever traffic signals are proposed at the <br /> intersection of the PUD driveway and 75th Street SW. The numbering designation and the <br /> location of each signal pole is presented on Figure 3, Signal Designation and Location Plan. <br /> Based on the soil information obtained in our explorations and the existing topography in the <br /> vicinity of the signal poles,we have divided the foundation design of signal poles into three <br /> separate cases. <br /> Case I: Based on our explorations BH-3 and HH-5, located in the vicinity of the Signal Poles 1 <br /> and 6, WSDOT standard plan foundations will be appropriate at these locations. For Standard <br /> Plan foundation design, required signal standard foundation depths and diameters will be a <br /> function of the total "XYZ"value of each mast arm, and the allowable lateral bearing stress of <br /> the surrounding soil. For Signal Poles 1 and 6, allowable lateral bearing pressures of 1,500 psf <br /> should be used for the signal pole foundations. We recommend 3 or 4-foot diameter drilled <br /> shafts be used. <br /> Case II: Our exploration indicate that WSDOT Standard Foundation Plans will not be <br /> applicable at the location of Signal Poles 2 and 3; as very loose soils were encountered from the <br /> ground surface to a depth of 12.5 feet, as indicated by the boring log for BH-5,presented in the <br /> Appendix A, Figure A-6. Therefore, a non-standard signal pole foundation design is required. <br /> We understand that the design team desires to use conventional p-y method of lateral analysis <br /> (i.e., LPILE)to estimate shears, moments and deflections of the signal pole foundation. Soil <br /> parameters for use in LPILE analyses are provided in Figure 4. The soil parameters provided in <br /> Figure 4 may be used with LPILE for lateral structural analyses and design of the signal pole <br /> foundations. Parameters are provided for static and seismic, non-liquefied analyses. Since the <br /> signal poles are to be supported on single drilled shafts, group action in not a design <br /> consideration of lateral capacity of the drilled shafts. <br /> Case III: The soil information obtained from BH-6,presented in Appendix A, Figure A-7 <br /> suggests that WSDOT standard plans can be utilized to design foundations of Signal Poles 4 <br /> and 5. However, the close proximity of these signal poles to the top of the slope on the north <br /> side of the 75th Street SW requires special consideration for these signal poles. For Standard <br /> Plan foundation design,required signal standard foundation depths and diameters will be a <br /> function of the total "XYZ"value of each mast arm, and the allowable lateral bearing stress of <br /> the surrounding soil. For Signal Poles 4 and 5, an allowable lateral bearing pressure of 1,000 psf <br /> should be used for the signal pole foundations. Due to the close proximity of the slope on the <br /> north side of these signal poles, we recommend that the signal foundation be embedded one shaft <br /> diameter deeper than what is recommended in WSDOT Signal Standard Foundation Plans. We <br /> 2014-117 Final Geotechnical Report 11 HWA GEOSCIENCES INC. <br />