r <br /> • <br /> t! , <br /> EXHIBIT A <br /> Task 3 —Design <br /> During the Design task, select alternatives developed during Task 2— Pre-design will be <br /> progressed to detailed design. The Design task will include several subtasks that are <br /> described below. <br /> At this time, the level of effort(LOE) required for developing nonstructural items that are <br /> related to structural seismic mitigation (such as removing and reinstalling the <br /> roofing/flooring/partition for roof/floor diaphragm) is unknown. Also,the LOE does not <br /> presently include mechanical, electrical or plumbing related design work. The LOE can <br /> be better defined after completion of Task 2. The approximate LOE for nonstructural <br /> items has been captured in Task 6—Undefined Services and will be defined in writing <br /> after the completion of Task 2. <br /> Subtask 3.1 —50% Design Development <br /> AECOM will develop a 50% design drawing set for the selected upgrade alternatives. <br /> The design drawing set will include plans, notes, elevations and typical details. Also <br /> included in this task will be the development of an outline for the technical specifications, <br /> which are assumed to be in 1997 Construction Specifications Institute (CSI)format(i.e., <br /> 16 Divisions). AECOM will also prepare 50% construction cost estimates for each <br /> selected upgrade alternatives that will be submitted with the 50% design drawings. <br /> Subtask 3.2—Design Review Meetings <br /> AECOM will meet with the City at two Design Review Meetings at the City's office in <br /> Everett. Objectives for each Design Review Meeting include: <br /> • Design Review Meeting 1 (after 50% Design submittal): Discuss 50% design and <br /> further reduce alternatives to progress (if applicable); and <br /> • Design Review Meeting 2 (after Permit submittal): Discuss Permit package. <br /> Prior to each meeting, AECOM will prepare and distribute an agenda. If there is <br /> available time after the meeting, additional site visits will be conducted, as needed. After <br /> each meeting,AECOM will document decisions made during the meeting in meeting <br /> minutes and distribute to the City for review and concurrence. <br /> AECOM will be represented by up to two attendees at each design review meeting. <br /> Subtask 3.3— Permit Package <br /> AECOM will develop Permit Package. The Permit package will have sufficient technical <br /> information for building permit purposes. Also included in this task will be the <br /> development of a final construction cost estimate. Permit assistance is not included and <br /> could be addressed through Task 6— Undefined Services. <br /> Subtask 3.4— Permitting Support <br /> The City stated that required project permit(s) (i.e., building permit)will be obtained <br /> through the City permitting department. The City will be responsible for applying for and <br /> obtaining required project permits, with AECOM providing permitting support. Permitting <br /> support will include providing information and figures for permit application(s). AECOM <br /> does not anticipate attending permit in-take meetings for this project. <br /> J:\Projects\E\Everett,City of\Operations Building Seismic Upgrade\Project Management\Scoping\revised 03-18- <br /> 15\2_Draft Scope of Work_Operations Bld Seismic Upgrade 04-14-15.docx <br /> Page 5 of 8 <br /> 84 <br />