I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> At the end of each contractor cutoff payment period, the Contractor's representative shall I <br /> show the Engineer's representative in the field, that their record drawing set of"redlined as- <br /> built documents" are being kept up to date. Failure of contractor to keep as-built records up <br /> to date may result in delay of payment. <br /> Bid Item 3 &63: Contractor's Liaison <br /> Measurement and Payment: Lump Sum (LS) <br /> The lump sum bid item includes full compensation for providing an employee dedicated full- <br /> time as a Community Project Liaison to coordinate access and other needs of business <br /> owners and residents within the area affected by the project. Specific requirements are <br /> identified in Section 1-07.29. <br /> Measurement for Contractor's liaison shall be the ratio of the number of working days <br /> completed to the number of working days authorized in the Contract. , <br /> Bid Item 4& 64: Traffic Control Labor <br /> Measurement and Payment: Unit Price per Hour(HR) <br /> This unit price bid item includes all costs associated with traffic control labor as identified in <br /> 1-10.3 FLAGGING, SIGNS, AND ALL OTHER TRAFFIC CONTROL DIVICES of these <br /> Special Provisions. <br /> Furnish all personnel for flagging to control traffic, including pedestrians, during construction I <br /> operations in accordance with Section 1-10 of the Standard Specifications, the Plans, <br /> approved traffic control plans, these Special Provisions and as directed by the City. <br /> Bid Item 5& 65: Traffic Control —Off-Duty Police Officer I <br /> Measurement and Payment: Force Account (FA) <br /> This Force Account bid item shall be accomplished in accordance with 1-09.6 FORCE <br /> ACCOUNT; except, as modified below. <br /> The Force Account bid item has been included for compensation for the hiring of an Off-Duty <br /> Police Officer to direct traffic at signalized or 4-way stop intersections as noted in 1-10.1 <br /> TEMPORARY TRAFFIC CONTROL of these Special Provisions. <br /> Bid Item 6& 66: Maintenance and Protection of Traffic Control <br /> Measurement and Payment: Lump Sum (LS) I <br /> Measurement for Maintenance and Protection of Traffic Control shall be the ratio of the <br /> number of working days completed to the total number of working days authorized in the I <br /> Contract. <br /> This lump sum bid item includes the maintenance and protection of traffic control materials, <br /> tools, and equipment necessary to accomplish the Work in accordance with 1-10.3(2) <br /> TRAFFIC CONTROL PROCEDURES, including yet not limited to, signs, barricades, cones, <br /> flashers, reader boards, and temporary pavement markings. Also included is supervisory <br /> personnel for all labor for traffic control, and all cost associated with preparation and <br /> distribution of public notices involving parking, street access or traffic issues. <br /> Bid Item 7 & 67: Trench Excavation Safety Systems <br /> Measurement and Payment: Lump Sum (LS) <br /> Measurement for trench excavation safety systems shall be the ratio of pipe installed and <br /> backfilled to the total quantity of pipe listed on the Proposal. <br /> The lump sum bid item includes the costs directly allocated to the safety system for trenches I <br /> and all other excavations including, but not limited to, shoring, benching, bracing, excavation, <br /> sheeting, and trench box. This Work shall be accomplished in accordance with Divisions 1, <br /> Sewer 0 Division B—BID DESCRIPTIONS April,2020 <br /> WO No.—UP3691 SP-4 <br /> I <br />