I <br /> Revised 2021-01-19— <br /> Addendum No. 1 <br /> 2. Increase the number of working hours per shift, shifts per working day,working days per week, <br /> or the amount of Equipment, or any combination of the foregoing. ' <br /> 3. Reschedule activities. <br /> If requested by the Owner's Representative,the Contractor shall prepare a proposed schedule revision <br /> demonstrating a plan to make up the lag in progress and insure completion of the Work within the <br /> Contract Time. All actions taken to return the Project to the accepted schedule are at the Contractor's <br /> expense. <br /> The Contractor shall pay all costs incurred by the Owner that result from the Contractor's action to return <br /> the Project to its accepted schedule, including,but not limited to, additional,overtime, or third party <br /> inspection, design and construction management service costs. Contractor agrees that Owner shall deduct <br /> such charges from payments due the Contractor. It is further understood and agreed that none of the <br /> services performed by the Owner's Representative in monitoring,reviewing and reporting Project status <br /> and progress shall relieve the Contractor of responsibility for planning and managing construction Work <br /> in conformance with the construction schedule. I <br /> 5.2.4. Delays <br /> 5.2.4.1 General <br /> In the event of a Delay, the Contractor shall take immediate steps to minimize the Delay or avoid further <br /> Delay. The Contractor agrees it shall not make any Contract Claim or request for adjustment of Contract <br /> Time or Contract Sum based upon Delays for which it did not timely provide Notice to the Owner. <br /> 5.2.4.2 Bonuses <br /> If the Contract Documents provide the Contractor with a bonus or other incentive for early completion of <br /> a milestone or other completion point, Contractor assumes the risk of Delays caused wholly or partially <br /> by third parties. Owner shall not pay any bonus that Contractor would have achieved but for any and all <br /> Delays caused in whole or in part by a third party. By way of example only,the Contractor bears the risk <br /> of utility companies' failure to locate underground utilities accurately and the Contractor bears the risk of <br /> timely asking for the marking of the location of underground utilities. <br /> 5.3. SUSPENSION PROCEDURES <br /> The Owner may,at its convenience and at any time and without cause, suspend all or any part of the <br /> Work by notice in writing to the Contractor. The Work shall be resumed by the Contractor within five(5) <br /> days after receiving written notice from the Owner to do so. The Contractor will be allowed an increase <br /> in the Contract Sum or an extension of Contract Time,or both, directly attributable to any suspension in <br /> accordance with the Change Order procedures herein;provided,the Contractor shall not be entitled to an <br /> increase to the extent caused by the Contractor and provided that Contract Sum increases and Contract <br /> Time extensions for suspension caused by Third Parties or Force Majeure Events are limited as set forth <br /> in 12.4.3.4 Third Party Caused Delays and Force Majeure. <br /> 5.4. TERMINATION PROCEDURES <br /> 5.4.1. Termination by Owner for Default I <br /> The Owner may terminate the Contract upon written notice to Contractor and its surety whenever the <br /> Contractor is deemed to be in default or fails to fulfill,in a timely and proper manner,one or more <br /> Contract obligations, or is in violation of any provisions or covenants of the Contract. Termination shall <br /> be effective upon receipt of such notice by the Contractor. <br /> For purposes of this paragraph,the Contractor shall be deemed to be in default upon the occurrence of <br /> any one or more of the following events: <br /> 1. If Contractor is bankrupt or insolvent. <br /> 2. If Contractor makes a general assignment for the benefit of creditors. 1 <br /> General Conditions—007200-18 <br /> 1 <br />