I <br /> Payment for Over-excavation shall be based on the unit price named in the <br /> proposal. Payment shall be considered full compensation for all tools, equipment, <br /> labor, materials, and incidentals to excavate beyond the limits shown in the <br /> contract drawings. Contractor shall receive direction/permission from Owner prior <br /> ' to utilizing this bid item. <br /> Progress payments for Over-excavation will be based on the full completion of each <br /> unit price, as approved by the OWNER. <br /> 10.11. Haul Offsite for Disposal <br /> Measurement and Payment: Cubic Yards <br /> Payment for Haul Offsite for Disposal shall be based on the unit price named in the <br /> proposal. Payment shall be considered full compensation for all tools, equipment, <br /> labor, materials, and incidentals to haul excavated material off-site. <br /> Progress payments for Haul Offsite for Disposal will be based on the full completion <br /> of each unit price, as approved by the OWNER. <br /> 11.12. Existing Reservoir 2 Demolition and Pipe Abandonment <br /> Measurement and Payment: Lump Sum <br /> Payment for Existing Reservoir 2 Demolition and Pipe Abandonment shall be based <br /> on the lump sum unit price named in the Proposal, which payment shall be <br /> considered full compensation for all tools, equipment, labor, materials, and <br /> incidentals necessary to complete this work as specified herein; including <br /> ' demolition of existing Reservoir 2, and existing pipe abandonment. <br /> Progress payments for Existing Reservoir 2 Demolition and Pipe Abandonment will <br /> be based on the percentage of this Work completed, as approved by the OWNER. <br /> HMA CL%" PG 58H-22 Grind and Overlay <br /> ' Measurement and Payment: Square Yards <br /> Payment for HMA CL 1/2" PG 58H-22 Grind and Overlay shall be based on the unit <br /> price named in the Proposal,which payment shall be considered full compensation <br /> for all tools, equipment, labor, materials, and incidentals necessary to complete <br /> this work as specified herein: including removal of bituminous pavement in the <br /> areas and to the depths defined in the drawings, furnishing and installing HMA CL. <br /> %" PG 58H-22 and tack oil: grading and compaction of asphalt concrete pavement; <br /> ' and compaction and testing of asphalt concrete pavement. Restoration of <br /> pavement markings and striping shall be incidental to the unit cost. The timing of <br /> this work shall comply with the City of Everett requirements. <br /> Replacement of Reservoir 2 Measurement and Payment <br /> 1 WO# UP3658 01 22 00-7 <br />