Mr. Mark Thunberg <br />Snohomish County Property Management <br />Plan Check Number: B1802-011, First Review (Structural) <br />June 18, 2018 <br />Foundation System: <br />12. The design for the shear wall foundations is provided in Section 4.2 of the structural <br />calculations. The calculations appear substantially incomplete. Additional documentation <br />substantiating the design should be submitted for review. The additional documentation <br />should include but is not limited to: input modeling criteria including material strengths and <br />cracked section properties; complete loading criteria for all footings; documentation of load <br />combinations including vertical seismic effects per ASCE 7-10 Section 12.4.2.2; calculations for <br />the shear and flexural design of the footings. See IBC Sections 1604.1, 1604.4, and 1613.1. <br />13. The "Location B" footing appears to respresent the foundation at Grid 1.5-K/12.1-13.1. The <br />size of the footing in the calculations appears inconsistent the drawings. At a minimum, the <br />south side of the footing appears to extend significantly farther than shown in the drawings. <br />The design of the footing should be reviewed and revised as needed. See IBC Section 1604.4. <br />14. The shear wall foundation at Grid C/8-11 includes micropiles at each end. The embedment of <br />the piles into the foundation is shown in Sections 10/S-502 and 15/S-502. The following <br />comments should be addressed: <br />a. Sheet S-200 specifies that the piles shall be cored through the existing footings. This <br />should be shown in one of the sections. See IBC Sections 107.2.1. <br />b. Calculations substantiating the capacity of the piles should be submitted for review. See <br />IBC Section 1604.1. <br />c. The sections show the piles embedding for most of the foundation depth. The piles do not <br />appear to include supplemental reinforcement connecting them to the foundation. <br />Calculations substantiating the load transfer to the piles for compression and uplift should <br />be submitted for review. See IBC Sections 1604.1 and 1604.4. <br />15. Additional documentation for the design of the shear wall foundation at Grid C/8-11 should be <br />submitted for review. See IBC Section 1604.4. The following comments should be addressed: <br />a. The foundation appears to be designed as a monolithic element. However, the foundation <br />encases three existing gravity footings. The foundation should be evaluated considering its <br />actual geometry, including discontinuities in its structure. <br />b. The foundation is anticipated to have rigid bearing zones at the ends due to the micropiles. <br />The foundation shall be designed as needed by analysis to span between the ends and <br />distribute vertical loads to the piles. <br />c. The load path between the shear wall and the continuous sides of the foundation shall be <br />substantiated. <br />Gravity System: <br />16. Section 1.2.3 provides gravity loading criteria for the gravity system analysis. See IBC Sections <br />1604.4, 1606, and 1607. The following comments should be addressed: <br />a. Level 02 includes an opening and framing for a stairway at Grid 3-K/12.1-13.1 that is not <br />included in the model. The framing plan should be revised and the design verified. <br />b. The second and fourth floors indicate a live load of 80 psf. The areas carry significant <br />areas of 100 psf live load for assembly loading per Sheets 5-102 and S-103. The analysis <br />appears based on use of an average value, which is not appropriate as some framing <br />age 4 of 11 <br />CITY OF EVERETT • 3200 Cedar Street • Everett, WA 98201 • (425) 257-8810 • Fax (425) 257-8857 <br />