November 23,2021 1 <br /> Replace Section 1-08.9 Liquidated Damages in its entirety with the following: <br /> Time is of the essence of the Contract. Delays inconvenience the public, obstruct other <br /> work, interfere with and delay commerce, and increase risk. Delays also cost taxpayers <br /> undue sums of money, adding time needed for administration, engineering, inspection, and <br /> supervision. I <br /> Accordingly, the Contractor agrees to pay liquidated damages for each calendar day beyond <br /> the number of calendar days established for Physical Completion. <br /> ***Physical Completion is defined in Section 1-01.3. The day the Engineer determines that <br /> the Work is physically complete, the Engineer will notify the Contractor in writing of the <br /> Physical Completion Date. *** I <br /> Liquidated damages will not be assessed for any days for which an extension of time is <br /> granted. No deduction or payment of liquidated damages will, in any degree, release the <br /> Contractor from further obligations and liabilities to complete the entire Contract. <br /> 1-08.9(1) City-Port Agreement Liquidated Damages <br /> (******) I <br /> ***Liquidated damages will be assessed if any of the following conditions occur: <br /> 1) $10,000 for each calendar day after Substantial Completion Date or June 1, 2022, <br /> whichever occurs first until substantial completion is achieved. <br /> 2) $10,000 for each calendar day after the City-Port Agreement Expiration Date has <br /> occurred. <br /> This reimbursement shall not apply to the extent that the Contractor is entitled under the <br /> Contract Documents to an extension of time to achieve substantial or physical <br /> completion. *** <br /> DIVISION 7 - DRAINAGE STRUCTURES, STORM SEWERS, SANITARY SEWERS, WATER I <br /> MAINS, AND CONDUITS <br /> Add the following: I <br /> 7-12 VALVES FOR WATER MAINS <br /> 7-12.3 Construction Requirements I <br /> Supplement 7-12.3 by adding the following: <br /> Install valve box centered on the operator nut. I <br /> Provide 3-inch-thick x 2-feet x 2-feet HMA concrete pad around valve boxes located within <br /> gravel surface. <br /> Provide one valve stem extension, minimum 12-inch length, in accordance with COE <br /> Standard Drawing No. 505 when the top of the valve operating nut is more than three feet <br /> below finished grade. I <br /> POE Combined Sewer Main Imp. Addendum No. 1 <br /> Work Order#UP3768 Page 8 of 12 <br /> I <br />