• <br /> Mr. John Bierly <br /> Wing Point Associates <br /> Plan Check Number: B2003-043, First Building Review <br /> May 14, 2020 <br /> 21.The Roof Framing Plan includes a new Penthouse. See IBC Section 107.2.1 and WSEC-15 Table <br /> C402.1.3. The following comments should be addressed: The penthouse has been <br /> removed. <br /> a. The Wall Type"Exterior-6"should include insulation with a minimum thermal rating of R-13 <br /> plus R-l0ci. Note that the framing in the Wall Schedule (i.e., metal studs) is not consistent <br /> with the Section Note Schedule in Section S1/A-10 (i.e., 2x6 wood studs). <br /> b. The SE roof should specify a minimum thermal rating of R-38ci. <br /> 22.The Roof Framing Plan on Sheet A-6 specifies a new skylight south of the Penthouse. The <br /> required maximum thermal rating (i.e., maximum U-factor) should be specified. See IBC <br /> Section 107.2.1 and WSEC-15 Table C402.4. The skylight has been removed. <br /> Miscellaneous: <br /> 23.The exterior doors at Lobby 1007 on Sheet A-3 and the doors throughout the 2nd Floor Plan on <br /> Sheet A-5 appear to include adjacent windows. It is anticipated that some of the doors, such <br /> as the exterior doors, may also include windows. Elevations for the doors and windows should <br /> be included in the drawings. The elevations should specify safety glazing where required. See <br /> IBC Sections 2406.4.1 and 2406.4.2. The door schedule showed, and continues to show, <br /> door elevations for all interior doors and specifies safety glass at all doors with <br /> glazed panels or sidelights. The exterior doors at 1007 have been elevated on <br /> 24. Restrooms 2004 and 2005 include more than one water closet. The 2nd Floor Plan on Sheet A-5 <br /> should be revised to specify floor drains. See UPC-15 Section 418.3(1). Floor drains have <br /> been added. <br /> 25.The Roof Framing Plan on Sheet S2.4 shows multiple new small openings that are presumed to <br /> be mechanical penetrations. The openings should be shown in the Roof Plan on Sheet A-6. <br /> See IBC Section 107.2.1. These were for existing roof top units that initially were to be <br /> replaced, but subsequently most have been retained. Units and associated <br /> ductwork are shown on A5 and A6,as well as on S2.4(some mis located openings <br /> have been corrected). <br /> Structural <br /> General: <br /> 1. Structural and geotechnical special inspections are required for this project. A list of the <br /> required inspections is provided in Note 12 of the General Structural Notes on Sheet S1.1. The <br /> table should be revised to specify the extent of each inspection (e.g., continuous, periodic). <br /> See IBC Sections 107.1 and 1704.3.1. A new sheet S1.3 has been created for the special <br /> inspection extents. <br /> 2. The project includes work that will be performed on the premises of fabricators'shops. Special <br /> inspections are required to be performed by the fabricators unless they are registered and <br /> 0 3200 Cedar Street 0 425.257.8810 0 everetteps@everettwa.gov <br /> Everett,WA 98201 425.257.8857 fax everettwa.gov/permits <br /> Page 6 of 9 <br />