<br /> Section 01 22 20 MEASUREMENT AND PAYMENT
<br /> backfill material around the outside of the manhole, furnishing and placing
<br /> concrete base for manhole with reinforcing bars, furnishing and placing epoxy
<br /> ' grout as shown on the Drawings, and placing and compacting foundation
<br /> material at the bottom of the manhole.
<br /> The cost to furnish the foundation material is included under the Foundation
<br /> Material bid item.
<br /> Bid Item 22. Manhole, Type 3, 72-Inch
<br /> ' The unit Contract Price bid per each (EA)for"Manhole, 72-Inch" shall
<br /> constitute full compensation for all Work, labor, materials, tools, and
<br /> equipment necessary to furnish and install the manhole as shown on the
<br /> Plans or as required by the Specifications, and includes, but is not limited to
<br /> excavation, haul and proper disposal of excavated materials, installing
<br /> manhole, placing and compacting native or import backfill material around the
<br /> t outside of the manhole, and placing and compacting foundation material at
<br /> the bottom of the manhole.
<br /> The cost to furnish the foundation material is included under the Foundation
<br /> Material bid item.
<br /> Bid Item 23. Manhole, 84-Inch
<br /> ' The unit Contract Price bid per each (EA)for"Manhole, 84-Inch" shall
<br /> constitute full compensation for all Work, labor, materials, tools, and
<br /> equipment necessary to furnish and install the manhole as shown on the
<br /> ' Plans or as required by the Specifications, and includes, but is not limited to
<br /> excavation, haul and proper disposal of excavated materials, installing
<br /> manhole, placing and compacting native or import backfill material around the
<br /> outside of the manhole, and placing and compacting foundation material at
<br /> the bottom of the manhole.
<br /> The cost to furnish the foundation material is included under the Foundation
<br /> Material bid item.
<br /> Bid Item 24. Manhole Sump Pump
<br /> The unit Contract Price per each (EA) for"Manhole Sump Pump" shall
<br /> ' constitute full compensation for all Work, labor, materials, tools, and
<br /> equipment necessary to furnish and install the sump pump as shown on the
<br /> Plans or as required by the Specifications, and includes, but is not limited to
<br /> pump sump, pump, 2-inch HDPE pump effluent piping to SDMH, excavation,
<br /> haul and proper disposal of excavated materials for installation of effluent
<br /> piping, trench backfill and trench asphalt patch per COE Standard Plans 326
<br /> ' and 614, coring and extending effluent piping in SDMH and packing annular
<br /> space with non-shrink grout.
<br /> Electrical conduit(s) and wiring for pump and controls are included in the
<br /> ' Electrical bid item.
<br /> Bid Item 25. Bollards
<br /> The unit Contract Price per each (EA)for"Bollards" shall constitute full
<br /> compensation for all Work, labor, materials, tools, and equipment necessary
<br /> to furnish and install bollards as shown on the Plans or as required by the
<br /> Specifications, and includes, but is not limited to excavation, haul and proper
<br /> City of Everett 01 22 20-15 January 2022