WORK ELEMENT 14 - CONSTRUCTION PHASE SUPPORT <br />The construction working days is assumed to be 310 and this work element includes the <br />following tasks; <br />TASK 14.1 CONSTRUCTION MANAGEMENT <br />TASK 14.1.1 Project Management <br />This Task includes administration of the contract between the CONSULTANT and the CITY, <br />preparation of progress reports for the PROJECT. It also includes all administrative services <br />needed to coordinate with the sub-CONSULTANT(s) and to monitor the PROJECT for scope, <br />schedule, budget, and quality. The following are the categorized activities associated with this <br />Task: <br />1. Progress Reports and Invoicing - progress reports will contain a narrative that <br />identifies and describes significant activities performed in the previous period and <br />significant upcoming activities along with the monthly invoice; <br />2. Coordination with the CM Construction Engineering Supervisor and Office Engineer <br />(OE) to assess and assist with staff augmentation when needed. <br />3. Construction Team Management - management of scope, schedule, budget, quality; <br />and, and immediate notification of the CM Construction Engineering Supervisor if <br />changes are warranted. <br />4. Management of Sub -consultants. <br />Assumptions: <br />1. The CITY will manage all activities related to the construction contract advertisement <br />and execution. <br />2. The CITY will provide a project manager to respond to the CONSULTANT <br />questions and approval for any potential contract changes, material over -runs, and <br />differing site conditions. <br />Deliverables: <br />1. Progress Reports and review with CITY PM <br />2. Monthly Invoicing <br />TASK 14.1.2 Pre -construction Services <br />The CONSULTANT will provide pre -construction services prior to the Contractor mobilization. <br />Services for the following activities will be provided: <br />Page I 6 <br />City of Everett — Edgewater Bridge Replacement <br />