I <br /> City of Everett 00 72 00 - 45 <br /> Water Filter Plant Portal 4 Improvements WO# 3755 <br /> 2. The nature and circumstances giving rise to the Notice; <br /> 3. The Contract provisions relating to,but not limited to,the event,incident,and direction; <br /> 4. The estimated dollar cost,if any,of the Extra Work,or Delay,or both and how that estimate was <br /> determined;and <br /> 5. An analysis of the schedule showing the schedule change or disruption if the Contractor is <br /> asserting a schedule change or disruption. <br /> Throughout any work related to a Notice,the Contractor shall keep complete and accurate records of <br /> costs,expenses,and time incurred for which Contractor will or may seek an adjustment. Contractor <br /> waives and is stopped from seeking an adjustment of Contract Sum or Contract Time where Contractor <br /> fails to keep and maintain cost,timekeeping,and scheduling records segregated and contemporaneously <br /> allocated to the subject work for which an adjustment is sought. For example,failure to keep <br /> contemporaneous labor and equipment time records specifically and only allocated to each item of <br /> claimed Extra Work shall constitute a waiver of any Contract Claim for reimbursement or additional <br /> Contract Time for each such item of Extra Work. The Contractor shall permit the Owner access to these <br /> and any other records needed for evaluating requests for additional Contract Time or Contract Sum. <br /> 11. DIFFERING SITE CONDITIONS <br /> Upon discovery and before such conditions are disturbed,the Contractor shall promptly provide Notice to <br /> the City's Representative of: <br /> 1. Pre-existing subsurface or latent physical conditions at the site differing materially from <br /> those indicated in this Contract,or <br /> 2. Pre-existing unknown physical conditions at the site,of an unusual nature,differing <br /> materially from those ordinarily encountered and generally recognized as inhering in <br /> work of the character provided for in this Contract. <br /> ' Upon written request,the City's Representative shall determine whether the actual conditions <br /> encountered by the Contractor conditions are materially different and, if so,are the cause of a material <br /> increase or decrease in the Contractor's cost of performance of the Work,or extend the duration of the <br /> critical path of the schedule. Upon such determination,the City's Representative will make an adjustment <br /> of Contract Sum or Contract Time,as appropriate. Extensions of Contract Time will be evaluated in <br /> accordance with 5.2.2.2 Extensions of Contract Time. <br /> The City's Representative's determination that differing site conditions do not exist and/or the appropriate <br /> adjustment in Contract Sum or Contract Time(if any)shall be final. If there is a decrease in the cost or <br /> time required to perform the Work,failure of the Contractor to notify the City's Representative of the <br /> differing site condition shall not affect the City's right to make an adjustment in the Contract Sum or <br /> Contract Time. Additionally,no Contract Claim or adjustment of Contract Sum or Contract Time shall <br /> be allowed unless the Contractor has followed the procedures provided for in this Contract,including,but <br /> not limited to,furnishing timely Notice of the event and its effect on Contract Time and Contract Sum as <br /> ' required herein. <br /> Contractor shall in no event be entitled to a Contract Claim or adjustment of Contract Sum or Contract <br /> Time based on an allegation that the pre-existing subsurface or latent physical conditions at the site differ <br /> materially from those indicated in this Contract unless Contractor establishes that it reasonably relied on <br /> the conditions indicated in this Contract when making its bid,that the actual conditions encountered on <br /> the site differed materially from those indicated in this Contract,and that such materially-different <br /> conditions were not foreseeable at the time of its bid. <br /> I <br /> 00 72 00 - 45 GENERAL CONDITIONS <br />