I <br /> City of Everett 00 72 00 - 46 <br /> Water Filter Plant Portal 4 Improvements WO# 3755 <br /> 12. CONTRACT CLAIMS <br /> 12.1 GENERAL I <br /> If the Contractor requests or believes for any reason that it is entitled to an adjustment of Contract Sum or <br /> Contract Time,or if the Contractor has a Dispute with the Owner and wants the Owner to take some <br /> action,or refrain from taking action,the Contractor shall file a Contract Claim as provided in this section. <br /> A timely and complete Contract Claim is a condition precedent to any entitlement by the Contractor to an <br /> adjustment of Contract Sum or Contract Time. No Contract Claim shall be allowed unless the Contractor <br /> has given Notice as required by 10. NOTICE TO OWNER and/or 11. DIFFERING SITE <br /> CONDITIONS and otherwise fully complies with the requirements of this section 12.CONTRACT <br /> CLAIMS. The Contractor waives any Contract Claim if: (a)Notice was not timely given in accordance <br /> with the requirements of 10. NOTICE TO OWNER and/or 11. DIFFERING SITE CONDITIONS; <br /> (b)the Owner's Representative is not afforded reasonable access by the Contractor to complete records, <br /> including,but not limited to,correspondence,job diaries,and actual cost and additional time incurred; (c) <br /> a Contract Claim is not timely filed as required by the General Conditions;or(d)adequate,accurate, <br /> contemporaneous and segregated supporting time and expense records are not kept and maintained. The <br /> fact that the Contractor provided proper and timely Notice,provided a properly filed Contract Claim,or <br /> provided the Owner's Representative access to records of actual cost, shall not in any way be construed as <br /> proving or substantiating the validity of the Contract Claim. If the Owner determines the Contract Claim <br /> has merit in whole or in part,the Owner's Representative will make an adjustment of Contract Sum or <br /> Contract Time required for the work,or both. If the Owner's Representative finds the Contract Claim to <br /> be without merit,no adjustment will be made. <br /> The Contractor shall keep full,complete,accurate and contemporaneous records of the costs and <br /> additional time incurred for any alleged Contract Claim. The Contractor shall permit the Owner's <br /> Representative to have access to those records and any other records as may be required by the Owner's <br /> Representative to determine the facts or contentions involved in the Contract Claim. Owner is not <br /> obligated to respond to a Contract Claim unless the Contractor is in full compliance with all the <br /> provisions of the General Conditions and the formal Contract Claim document has been submitted. <br /> Full compliance by the Contractor with the provisions of this section 12 is a contractual condition <br /> precedent to the Contractor's right to sue or seek any recovery against the Owner in any legal proceeding. <br /> 12.2 CONTENTS <br /> All Contract Claims filed by the Contractor shall be in writing,verified under penalty of perjury by an <br /> officer or principal of the Contractor,and in sufficient detail to enable the Owner's Representative to <br /> ascertain the basis and amount of the Contract Claim. All Contract Claims shall be submitted to the <br /> Owner's Representative. At a minimum,each Contract Claim must include: <br /> 1. A detailed factual statement of the Contract Claim for an adjustment of the Contract Sum or <br /> Contract Time, if any,providing all necessary dates,locations,and items of work affected by the <br /> Contract Claim. <br /> 2. The dates of all facts related to the Contract Claim. I <br /> 3. The name of each Owner's individual,official,or employee involved in or knowledgeable about <br /> the Contract Claim. <br /> 4. The specific provisions of the Contract that support the Contract Claim and a statement of the t <br /> reasons why such provisions support the Contract Claim. <br /> 5. If the Contract Claim relates to a decision of the Owner's Representative that the Contract leaves <br /> to the Owner's Representative's discretion or as to which the Contract provides that the Owner <br /> Representative's decision is final,the Contractor shall set out in detail all facts supporting its <br /> position relating to the decision of the Owner's Representative. <br /> 00 72 00 - 46 GENERAL CONDITIONS <br />