Laserfiche WebLink
1 Engineer will notify the Contractor in writing of the Substantial Completion Date. For <br /> 2 overruns in Contract time occurring after the date so established, the formula for <br /> 3 liquidated damages shown above will not apply. For overruns in Contract time occurring <br /> 4 after the Substantial Completion Date, liquidated damages shall be assessed on the <br /> 5 basis of direct engineering and related costs assignable to the project until the actual <br /> 6 Physical Completion Date of all the Contract Work. The Contractor shall complete the <br /> 7 remaining Work as promptly as possible. Upon request by the Project Engineer, the <br /> 8 Contractor shall furnish a written schedule for completing the physical Work on the <br /> 9 Contract. <br /> 10 <br /> 11 1-09.GR1 <br /> 12 Measurement and Payment <br /> 13 <br /> 14 1-09.6.RTF <br /> 15 1-09.6 Force Account <br /> 16 (October 10, 2008 APWA GSP) <br /> 17 <br /> 18 Supplement this section with the following: <br /> 19 <br /> 20 The Contracting Agency has estimated and included in the Proposal, dollar amounts for <br /> 21 all items to be paid per force account, only to provide a common proposal for Bidders. All <br /> 22 such dollar amounts are to become a part of Contractor's total bid. However, the <br /> 23 Contracting Agency does not warrant expressly or by implication, that the actual amount <br /> 24 of work will correspond with those estimates. Payment will be made on the basis of the <br /> 25 amount of work actually authorized by Engineer. <br /> 26 <br /> 27 1-09.8.GR1 <br /> 28 Payment For Material On Hand <br /> 29 <br /> 30 1-09.8.INSTI.GR1 <br /> 31 The last paragraph of Section 1-09.8 is revised to read: <br /> 32 <br /> 33 1-09.8.OPT1.GR1 <br /> 34 (August 3, 2009) <br /> 35 The Contracting Agency will not pay for material on hand when the invoice cost is less <br /> 36 than $2,000. As materials are used in the work, credits equaling the partial payments for <br /> 37 them will be taken on future estimates. Each month, no later than the estimate due date, <br /> 38 the Contractor shall submit a letter to the Engineer that clearly states: 1) the amount <br /> 39 originally paid on the invoice (or other record of production cost)for the items on hand, 2) <br /> 40 the dollar amount of the material incorporated into each of the various work items for the <br /> 41 month, and 3) the amount that should be retained in material on hand items. If work is <br /> 42 performed on the items and the Contractor does not submit a letter, all of the previous <br /> 43 material on hand payment will be deducted on the estimate. Partial payment for materials <br /> 44 on hand shall not constitute acceptance. Any material will be rejected if found to be faulty <br /> 45 even if partial payment for it has been made. <br /> 46 <br /> 47 1-09.9(Payments).RTF <br /> 48 1-09.9 Payments <br /> 49 (January 19, 2022 APWA GSP) <br /> 50 <br /> 51 Section 1-09.9 is revised to read: <br /> 2023 PAVEMENT MAINTENANCE OVERLAY <br /> WO#3789 February 14,2023 33 <br />