Laserfiche WebLink
I <br /> 1 1-08.5.OptionA.RTF <br /> I2 1-08.5 Time for Completion <br /> 3 (January 19, 2022 APWA GSP, Option A) <br /> 4 <br /> I 5 Revise the third and fourth paragraphs to read: <br /> 6 <br /> 7 Contract time shall begin on the first working day following the Notice to Proceed Date. <br /> I 8 <br /> 9 Each working day shall be charged to the contract as it occurs, until the contract work is <br /> 10 physically complete. If substantial completion has been granted and all the authorized <br /> Ii 1 working days have been used, charging of working days will cease. Each week the <br /> 12 Engineer will provide the Contractor a statement that shows the number of working days: <br /> 13 (1) charged to the contract the week before; (2) specified for the physical completion of <br /> I <br /> 14 the contract; and (3) remaining for the physical completion of the contract. The <br /> 15 statement will also show the nonworking days and any partial or whole day the Engineer <br /> 16 declares as unworkable The statement will be identified as a Written Determination by <br /> 17 the Engineer. If the Contractor does not agree with the Written Determination of working <br /> I <br /> 18 days, the Contractor shall pursue the protest procedures in accordance with Section 1- <br /> 19 04.5. By failing to follow the procedures of Section 1-04.5, the Contractor shall be <br /> 20 deemed as having accepted the statement as correct. If the Contractor is approved to <br /> I <br /> 21 work 10 hours a day and 4 days a week (a 4-10 schedule) and the fifth day of the week <br /> 22 in which a 4-10 shift is worked would ordinarily be charged as a working day then the <br /> 23 fifth day of that week will be charged as a working day whether or not the Contractor <br /> I <br /> 24 works on that day. <br /> 25 <br /> 26 Revise the sixth paragraph to read: <br /> I 27 <br /> 28 The Engineer will give the Contractor written notice of the completion date of the contract <br /> 29 after all the Contractor's obligations under the contract have been performed by the <br /> I <br /> 30 Contractor. The following events must occur before the Completion Date can be <br /> 31 established: <br /> 32 1. The physical work on the project must be complete; and <br /> I <br /> 33 2. The Contractor must furnish all documentation required by the contract and required <br /> 34 by law, to allow the Contracting Agency to process final acceptance of the contract. <br /> 35 The following documents must be received by the Project Engineer prior to <br /> I <br /> 36 establishing a completion date: <br /> 37 a. Certified Payrolls (per Section 1-07.9(5)). <br /> 38 b. Material Acceptance Certification Documents <br /> I <br /> 39 c. Monthly Reports of Amounts Credited as DBE Participation, as required by the <br /> 40 Contract Provisions. <br /> 41 d. Final Contract Voucher Certification <br /> I <br /> 42 e. Copies of the approved "Affidavit of Prevailing Wages Paid" for the Contractor <br /> 43 and all Subcontractors <br /> 44 f. A copy of the Notice of Termination sent to the Washington State Department of <br /> I45 Ecology (Ecology); the elapse of 30 calendar days from the date of receipt of the <br /> 46 Notice of Termination by Ecology; and no rejection of the Notice of Termination <br /> 47 by Ecology. This requirement will not apply if the Construction Stormwater <br /> I 48 General Permit is transferred back to the Contracting Agency in accordance with <br /> 49 Section 8-01.3(16). <br /> I <br /> 2023 FEDERAL OVERLAY <br /> FEDERAL AID#STBGUL-2715(011) <br /> I <br /> WO#3788 March 2,2023 SP-59 <br />