Laserfiche WebLink
I <br /> 1 1-09.6.RTF I <br /> 2 1-09.6 Force Account <br /> 3 (October 10, 2008 APWA GSP) <br /> 4 <br /> I 5 Supplement this section with the following: <br /> 6 <br /> 7 The Contracting Agency has estimated and included in the Proposal, dollar amounts for <br /> I 8 all items to be paid per force account, only to provide a common proposal for Bidders. All <br /> 9 such dollar amounts are to become a part of Contractor's total bid. However, the <br /> 10 Contracting Agency does not warrant expressly or by implication, that the actual amount <br /> 11 of work will correspond with those estimates. Payment will be made on the basis of the <br /> 12 amount of work actually authorized by Engineer. <br /> 13 <br /> 14 1-09.9.GR1 <br /> I15 Payments <br /> 16 <br /> 17 1-09.9(Payments).RTF <br /> I18 1-09.9 Payments <br /> 19 (January 19, 2022 APWA GSP) <br /> 20 <br /> I21 Section 1-09.9 is revised to read: <br /> 22 <br /> I 23 The basis of payment will be the actual quantities of Work performed according to the <br /> 24 Contract and as specified for payment. <br /> 25 <br /> I 26 The Contractor shall submit a breakdown of the cost of lump sum bid items at the <br /> 27 Preconstruction Conference, to enable the Project Engineer to determine the Work <br /> 28 performed on a monthly basis. A breakdown is not required for lump sum items that <br /> I 29 include a basis for incremental payments as part of the respective Specification. Absent <br /> 30 a lump sum breakdown, the Project Engineer will make a determination based on <br /> 31 information available. The Project Engineer's determination of the cost of work shall be <br /> 32 final. <br /> 33 <br /> 34 Progress payments for completed work and material on hand will be based upon <br /> I 35 progress estimates prepared by the Engineer. A progress estimate cutoff date will be <br /> 36 established at the preconstruction conference. <br /> 37 <br /> I 38 The initial progress estimate will be made not later than 30 days after the Contractor <br /> 39 commences the work, and successive progress estimates will be made every month <br /> 40 thereafter until the Completion Date. Progress estimates made during progress of the <br /> I <br /> 41 42 work are tentative, and made only for the purpose of determining progress payments. <br /> The progress estimates are subject to change at any time prior to the calculation of the <br /> 43 final payment. <br /> 44 I 45 The value of the progress estimate will be the sum of the following: <br /> 46 1. Unit Price Items in the Bid Form —the approximate quantity of acceptable units of <br /> 47 work completed multiplied by the unit price. <br /> I <br /> 2023 FEDERAL OVERLAY <br /> FEDERAL AID#i STBGUL-2715(011)I <br /> WO#13788 March 2,2023 SP-61 <br />