Laserfiche WebLink
1A MONTHLY PROGRESS SCHEDULE UPDATES <br /> A. The Contractor is required to prepare and submit monthly Progress Schedule updates <br /> and to participate in monthly schedule update meetings with the Architect and Owner <br /> as described below. <br /> 1. Timely submission of updates is of significant and crucial importance to the <br /> management of the Project. Lack of, or late receipt of, updates diminishes their value <br /> to the Architect and Owner. If a monthly Progress Schedule update is not submitted <br /> to and reviewed with the Architect and Owner prior to the Contractor submitting its <br /> monthly Application for Payment; the monthly Schedule of Values amount for <br /> Progress Schedule updates may, at the Architect's sole judgment and discretion, <br /> be reduced from the Specified General Conditions by a unilateral Change Order <br /> (see Section 01 29 76, "Progress Payments -GCCM"). <br /> B. The Contractor shall prepare monthly Progress Schedule updates to reflect work progress <br /> achieved since the previous update. Historical performance data and/or records shall <br /> not be changed without approval of the Architect and Owner. <br /> C. The Contractor shall, in a second and subsequent report, incorporate any logic and <br /> duration changes that represent its revised planning, provided all such changes are <br /> identified and submitted to the Architect and Owner for comment in the narrative report <br /> required herein this section. <br /> D. The Contractor shall use and maintain a fixed end date when generating the required <br /> reports and diagrams for the Architect and Owner as specified by this section. The fixed <br /> end date shall be the Substantial Completion date. The fixed end date will be adjusted <br /> in subsequent updates only to reflect approved time extensions incorporated by Change <br /> Order. <br /> E. The Project shall be rescheduled each reporting period with: <br /> 1. An updated data date. <br /> 2. Actual start/finish dates. <br /> 3. Percent complete. <br /> 4. Remaining durations (for each activity in the "status" or"current file). <br /> F. Show changes occurring since the previous schedule submission, such as: <br /> 1. Any major changes in scope. <br /> 2. Activities modified since previous submission including, but not limited to, logic <br /> changes. <br /> 3. Revised projections for progress and completion, as applicable. <br /> 4. Any other identifiable changes. <br /> G. The Contractor shall account for all rain days,for major events,and similar excusable non- <br /> compensable delays, during which little or no work is progressed and that are <br /> acknowledged by the Architect and Owner, in the period within which the events occur. <br /> The Contractor may account for such delays within the Progress Schedule update by <br /> City of Everett Municipal Building February 3,2023 <br /> Everett Municipal Building Public Works Tenant Spec Sect 0132 16 <br /> Improvements 01 32 16-6 Construction Progress Schedule <br /> RFFP for GC/CM Services <br />