Schedule shall be prepared in sufficient detail and in consideration of, but not limited to, <br /> the following: <br /> 1. Preparation and submission of shop drawings, layout drawings, product data, <br /> material samples, and mock-ups. <br /> C. Update the Submittal Schedule monthly and submit to Architect's Representative. <br /> 1.6 SHORT INTERVAL SCHEDULE <br /> A. Short Interval Schedule: Prepare and update weekly a four (4) week Short Interval <br /> Schedule. Show previous week of actual progress (planned vs. actual performance). <br /> Forecast three (3) weeks of start and completion dates for each activity, task or event <br /> in comparison to the Progress Schedule. <br /> 1. Activities in the Short Interval Schedule shall relate directly to activities in the Progress <br /> Schedule. <br /> B. Format for the Short Interval Schedule should be similar to the sample form. However, <br /> the Contractor may submit an alternative format that must first be approved by the <br /> Architect and Owner. The format shall include comment annotation as necessary. <br /> C. Copies of the Short Interval Schedule shall be provided at the Construction Progress <br /> Meetings and will be used as a basis for discussion of progress and planned work at <br /> the meetings. <br /> PART 2— PRODUCTS (NOT USED) <br /> PART 3 —EXECUTION (NOT USED) <br /> END OF SECTION <br /> City of Everett Municipal Building February 3,2023 <br /> Everett Municipal Building Public Works Tenant Spec Sect 0132 16 <br /> Improvements 01 32 16-8 Construction Progress Schedule <br /> RFFP for GC/CM Services <br />