Manager's Fee shall be equitably adjusted on the same basis that was used to establish the Fee for the original Work,
<br /> and the Guaranteed Maximum Price shall be adjusted accordingly.
<br /> ARTICLE 7 COST OF THE WORK FOR CONSTRUCTION PHASE
<br /> § 7.1 Costs to Be Reimbursed
<br /> § 7.1.1 The term Cost of the Work shall mean the actual,net costs reasonably and necessarily incurred by the
<br /> Construction Manager in the proper performance of the Work,without overhead,profit,fee or markup. Such costs shall
<br /> be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost
<br /> of the Work shall include only the items set forth in Sections 7.1 through 7.7.
<br /> § 7.1.2 Where,pursuant to the Contract Documents,any cost is subject to the Owner's prior approval,the Construction
<br /> Manager shall obtain such approval in writing prior to incurring the cost.
<br /> § 7.1.3 Costs shall be at rates not higher than the standard rates paid at the place of the Project,except with prior
<br /> approval of the Owner.
<br /> § 7.2 Labor Costs
<br /> § 7.2.1 Wages or salaries of construction workers directly employed by the Construction Manager to perform the
<br /> construction of the Work at the site or,with the Owner's prior approval,at off-site workshops.
<br /> § 7.2.2 Wages or salaries of the Construction Manager's supervisory and administrative personnel are included in the
<br /> Specified General Conditions and not separately reimbursable.
<br /> § 7.2.2.1 Wages or salaries of the Construction Manager's supervisory and administrative personnel when performing
<br /> Work and stationed at a location other than the site,but only for that portion of time required for the Work are included
<br /> in the Specified General Conditions and not separately reimbursable.
<br /> § 7.2.3 Wages and salaries of the Construction Manager's supervisory or administrative personnel engaged at factories,
<br /> workshops or while traveling,in expediting the production or transportation of materials or equipment required for the
<br /> Work,are included in the Specified General Conditions and not separately reimbursable.
<br /> § 7.2.4 Costs paid or incurred by the Construction Manager,as required by law or collective bargaining agreements,for
<br /> taxes,insurance,contributions,assessments and benefits and,for personnel not covered by collective bargaining
<br /> agreements,customary benefits such as sick leave,medical and health benefits,holidays,vacations and pensions,
<br /> provided such costs are based on wages and salaries included in the Cost of the Work under Sections 7.2.1 through
<br /> 7.2.3.This does not include insurance required by the Contract Documents,which costs are included within the
<br /> Specified General Conditions.Costs paid or incurred by the Construction Manager for vacations,bonuses,travel,stock
<br /> options,deferred compensation,or discretionary payments to employees are not directly reimbursable.As part of the
<br /> GMP Amendment,the parties may agree to a wage burden rate for all workers,which will be fully burdened,including
<br /> all the wage-based costs,and fixed for the duration of the Contract time.Burden rates, including any agreed burden
<br /> rates,are subject to the Owner's audit to confirm that the burden has been correctly calculated and applied in
<br /> accordance with the Contract Documents.
<br /> § 7.2.5 If agreed rates for labor costs,in lieu of actual costs,are provided in this Agreement,the rates shall remain
<br /> unchanged throughout the duration of this Agreement,unless the parties execute a Modification.
<br /> § 7.3 Subcontract Costs
<br /> Payments made by the Construction Manager to Subcontractors in accordance with the requirements of the subcontracts
<br /> and this Agreement.The Construction Manager shall maintain a procedure for the review,processing and payment of
<br /> applications by the Subcontractors for progress and final payments,all in accordance with the terms and conditions of
<br /> the Contract Documents.The Construction Manager shall verify the completeness of all applications for payment and
<br /> assemble and check all supporting documentation required by the Contract Documents or by the subcontracts with
<br /> respect to each Application for Payment,including all lien waivers and releases.
<br /> ALA Document A1333 - 2019. Copyright © 1991, 2003, 2009, and 2019 by The American Institute of Architects. All rights reserved. The
<br /> "American Institute of Architects," "AIA," the AIA Logo, and "AIA Contract Documents" are registered trademarks and may not be used 2 1
<br /> without permission. This draft was produced by AIA software at 13:10:24 ET on 04/22/2021 under Order No.7856855196 which expires on
<br /> 05/01/2022, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms
<br /> of Service. To report copyright violations, e-mail copyright@aia.org.
<br /> User Notes: (1279676012)
<br />
|