Laserfiche WebLink
PGSF WMVD Storm and Combined Sewer Design Scope of Work 08-25-2023 <br /> <br />36 of 41 <br /> <br />Category 2: Sensitive information <br />Category 2: For official use only / disclosure permissible by law. <br />Activities/Approach: The Design Manager will lead this effort and will actively lead the design process <br />through regular meetings with the design team. This phase will also support the coordination of the <br />project design with the City through monthly workshops. Design standards and workflows for <br />BIM/CAD, drawing production, and specification production will be developed in this phase. <br />A project issues log sorted by facility area will be maintained by the Design Manager to manage <br />identification of design issues and their resolution. <br />This phase includes the following activities: <br />General Design Management <br />• Check on the design team progress and communicate results to project management. <br />• Verify QMP is followed, reviewers concur with work products, and maintain documentation of <br />QA/QC reviews, responses, and resolutions. <br />• Maintain ongoing communications with the subconsultants and monitor subconsultant <br />progress related to the technical execution of the design. <br />• Conduct internal design team coordination meetings. <br />• Manage internal resources to maintain project schedule and achieve contracted milestones. <br />• Identify scope changes that impact the project budget and schedule. Notify the Project <br />Manager of potential changes in scope and assist in documenting those changes. <br />• Regularly assess progress and earned value and maintain risk register. <br />• Guide design activities to maximize project progress. <br />• Coordinate progress reviews by the City, including collecting comments from the City’s <br />review, distributing review comments to facility and discipline leads, facilitating responses to <br />review comments, documenting responses to the City’s review comments, addressing any <br />subsequent issues resulting from the City’s review and addressing any subsequent issues <br />resulting from the response to the City’s review comments. <br />• Establish equipment numbering system, if needed. <br />• Maintain equipment list, if needed. <br />Workshops <br />• Conduct monthly workshops covering scheduled topics (see Meetings). <br />• Technical content of workshops will come from efforts in Predesign Work, Support Services, <br />and Final Design phases. This phase will include preparation of workshop presentation <br />materials, agendas, notes/summaries, and attendance. <br />BIM/CAD Management <br />• Define project CAD software standards, graphics standards, file naming conventions and <br />standards, and revision/iteration control. Document standards in a CAD Standards TM. <br />• Develop BIM Execution Plan (BXP) to guide the use of BIM tools over the life of the project. <br />Define project goals and BIM objectives, organizational roles and responsibilities, execution <br />process workflows, collaboration procedures and platforms, and model and drawing QC <br />procedures. <br />• As part of the development of the CAD Standards TM and BXP, conduct a workshop with the <br />City to confirm approach will meet City’s expectations. <br />• Implement and manage CAD Standards and BXP through the duration of the design. <br />• Conduct internal coordination meetings with BIM/CAD production team.