CITY OF EVERETT SPECIAL PROVISIONS <br /> <br />Beverly Lake Water Quality Retrofit Division 5 – SURFACE TREATMENTS August 2023 <br /> <br />AND PAVEMENTS <br />WO No. – UP3745 SP - 182 <br />5-06.3(6) Temporary Pavement Patching <br />The Contractor shall furnish, place and maintain temporary pavement patching as shown <br />on the Plans and at locations as directed by the Engineer, until such time as a permanent <br />patch of permanent paving can be made. <br />Provide a temporary patch as required to reopen roadway during construction as that <br />withstands existing traffic loads and volumes. Options include, and are not limited to, <br />cold mix asphalt (MC 250), hot mix asphalt (HMA CL 1/2”, PG 64-22), or secured steel <br />roadway plates. <br />Provide temporary asphalt patching where roadway or walk is needed for vehicular or <br />pedestrian traffic, during the construction period, until permanent pavement and <br />sidewalks can be constructed. <br />In the event that the temporary surface subsides after the initial placement, apply <br />additional MC 250 or HMA (as approved by the Engineer) as necessary to maintain the <br />surface. <br />Stockpile of plant mix and crushed surfacing for temporary patching shall be provided <br />on the site by the Contractor. <br />Prior to final restoration of the pavement, the Contractor shall be responsible for <br />removing and disposing of temporary pavement patching materials. <br />5-06.3(7) Incidental Pavement Patching <br />Incidental pavement patching shall be done only at the direction of the Engineer for <br />patching and restoring areas between the back of new sidewalks and adjacent asphalt <br />driveways, paving ramps at the ends of sidewalks, and gutters that are adjusted to <br />grade. <br />Asphalt for incidental pavement patching shall be HMA CL 1/2”, PG 64-22. <br />5-06.4 Measurement <br />Bid items of Work completed pursuant to the Contract Documents will be measured as <br />described in Division B – Bid Item Descriptions of these Special Provisions and Section 1-09 <br />MEASUREMENT AND PAYMENT of the Standard Specifications. <br />5-06.5 Payment <br />Payment for bid items of Work completed pursuant to the Contract Documents will be as <br />described in Division B – Bid Item Descriptions of these Special Provisions and Section 1-09 <br />MEASUREMENT AND PAYMENT of the Standard Specifications. <br />