Laserfiche WebLink
LE LOEB <br /> ELECTRIC <br /> 4.4 Arc Flash Relay Installation Timeline <br /> • Prior to Outage <br /> o Testing of relays & CT's to occur within 10 days of outage at VEEC shop. <br /> ■ Perform CT Ratio and Excitation <br /> o Loeb to ship Arc Flash Relay and UPS to VEEC/EC <br /> o Pre-Outage enclosure checklist must be completed, see appendix R. <br /> o Install control box with relay within 10 feet of the Main breaker and UPS <br /> o Install three phase disconnect switch <br /> o Install conduit for fiber loop,voltage, control, BMS and CT wiring (install as much as <br /> possible,final conduit connections to be made with switch gear and switch boards <br /> when deenergized). <br /> • During Outage <br /> o Complete relay installation <br /> o Install fiber loops <br /> o Install CT's <br /> o Complete execution checklist. See appendix S. <br /> o Perform testing in compliance with Appendix A prior to energization <br /> o Follow Switching procedures outlined in Appendix K prior to energization <br /> • Post Outage <br /> o After all work is completed and deficiencies found. Review all deficiencies fixed and all follow up <br /> items with Amazon team. Central/Regional and Site RME. <br /> o Amazon EE or owner's representative to acknowledge and sign off on any changes made to <br /> schematics/wiring, relay logic and All testing and functional testing. <br /> 5.0 Infrared Scanning <br /> 5.1 Infrared Scanning Scope of Work <br /> IR scanning will only be required if correction of known deficiency was part of scope for specific outage. <br /> 5.2 Infrared Scanning Division of Responsibilities <br /> • Amazon <br /> o Provide list of known IR deficiencies prior to site walks for correction. <br /> • Loeb <br /> o Provide professional project management services. <br /> o Lead all communications between stakeholders, including but not limited to: <br /> • Amazon Corporate. <br /> ■ Amazon Site Facility. <br /> • Provide Thermal and Visual Inspection report upon completion. <br /> • VEEC <br /> o Provide a certified infrared thermographer to return to site within (24) hours to scan repaired <br /> thermal deficiencies. <br /> 5.3 Infrared Scanning Timeline <br /> • Scan must occur following day during peak operating hours. <br /> 211Page <br />