Page 103 of4/19/2024 12:03 PMEverett WFPDB GMP WIP4211GMPWIP 110
<br />TotalTruckingGeneralSubConst MatlsPerm MatlsEquipmentTotal LaborBurdenBase Labor
<br />63,000.000.000.000.000.0063,000.000.000.000.000.00Total
<br />63,000.000.000.000.000.0063,000.000.000.000.000.00U. Cost
<br />WA Bridge ConstructionWA0201WC:10Hrs/Shift:50 Hour Week - (5@10)510Calendar:
<br />TotalActual UCTax/OT %Unit CostUnitQuantityPcs/WsteDescriptionResource
<br />48,000.0048,000.00100.0048,000.00LS1.001.00PLYPRCSS - HDPE Tanks2-434008
<br />10,000.0010,000.00100.0010,000.00LS1.001.00PLYPRCSS - Day Tanks2-434012
<br />5,000.005,000.00100.005,000.00LS1.001.00PLYPRCSS - HDPE Tank Freight2HDPEFRT
<br />EAUnit:3.00Quantity:Fluoride Tank Install795-10Activity:
<br />TotalTruckingGeneralSubConst MatlsPerm MatlsEquipmentTotal LaborBurdenBase Labor
<br />15,936.580.000.000.000.000.001,272.9114,663.675,349.669,314.01Total
<br />5,312.190.000.000.000.000.00424.304,887.891,783.223,104.67U. Cost
<br />$/ShiftShifts/UnitUnits/ShiftShifts$/Crew HourUnits/Crew HrCrew Hrs/UnitCrew $/Unit
<br />3,984.14501.33330.75004.0000398.41450.075013.33335,312.1933
<br />Base Labor/UnitTotal Labor/MHMH/UnitUnit/MHManhours
<br />3,104.6700122.197340.00000.0250120.0000
<br />WA Bridge ConstructionWA0201WC:10Hrs/Shift:50 Hour Week - (5@10)510Calendar:
<br />1.00Equipment Pcs:3.00Labor Pcs:40.00Crew Hrs:100.00Eff:13.3333HUProd:Mechanical Crew - 3 MenMC3Crew:
<br />TotalActual UCTax/OT %Unit CostUnitQuantityPcs/WsteDescriptionResource
<br />1,272.9131.82109.7530.68HR40.001.00Ford F450 Pipefitter8TKJ450P
<br />4,976.48124.41110.0071.89MH40.001.00Pipefitter ForemanPFF
<br />9,687.19121.09110.0069.89MH80.002.00Pipefitter JourneymanPFJ
<br />LSUnit:1.00Quantity:Purchase Chem Pumps795-20Activity:
<br />WA Bridge ConstructionWA0201WC:10Hrs/Shift:50 Hour Week - (5@10)510Calendar:
<br />TotalActual UCTax/OT %Unit CostUnitQuantityPcs/WsteDescriptionResource
<br />15,000.0015,000.00100.0015,000.00LS1.001.00Chem Pumps2-432420
<br />EAUnit:2.00Quantity:Install Chemical Metering Pumps & Skids795-30Activity:
<br />TotalTruckingGeneralSubConst MatlsPerm MatlsEquipmentTotal LaborBurdenBase Labor
<br />10,960.100.000.000.000.000.001,272.919,687.193,536.526,150.67Total
<br />5,480.050.000.000.000.000.00636.464,843.601,768.263,075.34U. Cost
<br />$/ShiftShifts/UnitUnits/ShiftShifts$/Crew HourUnits/Crew HrCrew Hrs/UnitCrew $/Unit
<br />2,740.02502.00000.50004.0000274.00250.050020.00005,480.0500
<br />Base Labor/UnitTotal Labor/MHMH/UnitUnit/MHManhours
<br />3,075.3350121.089940.00000.025080.0000
<br />WA Bridge ConstructionWA0201WC:10Hrs/Shift:50 Hour Week - (5@10)510Calendar:
<br />1.00Equipment Pcs:2.00Labor Pcs:40.00Crew Hrs:100.00Eff:20HUProd:Mechanical Crew - 2 MenMC2Crew:
<br />TotalActual UCTax/OT %Unit CostUnitQuantityPcs/WsteDescriptionResource
<br />1,272.9131.82109.7530.68HR40.001.00Ford F450 Pipefitter8TKJ450P
<br />9,687.19121.09110.0069.89MH80.002.00Pipefitter JourneymanPFJ
<br />EAUnit:1.00Quantity:False Floor Install/Remove795-40Activity:
<br />TotalTruckingGeneralSubConst MatlsPerm MatlsEquipmentTotal LaborBurdenBase Labor
<br />14,090.830.000.000.005,425.000.000.008,665.833,224.645,441.19Total
<br />14,090.830.000.000.005,425.000.000.008,665.833,224.645,441.19U. Cost
<br />$/ShiftShifts/UnitUnits/ShiftShifts$/Crew HourUnits/Crew HrCrew Hrs/UnitCrew $/Unit
<br />4,696.94333.00000.33333.0000288.86100.033330.00008,665.8300
|