Laserfiche WebLink
Edgewater Creek Bridge Replacement November 2023 162 8-02.4.OPT3.DOCX 1 (******) 2 Installed topsoil, mulch and soil amendments will be measured by the square yard. 3 4 8-02.5.GR8 5 Payment 6 7 8-02.5.INST1.GR8 8 Section 8-02.5 is supplemented with the following: 9 10 8-02.5.OPT6.DOCX 11 (******) 12 “Fine Compost”, per Square Yard. 13 The unit Contract price per Square yard for “Fine Compost” shall be full compensation for 14 furnishing and incorporating the compost as a soil amendment pursuant to Soil 15 Restoration Detail on Planting Plan. 16 17 “Soil Amendment”, per square yard. 18 19 8-02.5.SA1.DOCX 20 (******) 21 “Park Restoration”, lump sum. 22 The lump sum Contract price for “Park Restoration” shall be full compensation for all costs 23 incurred by the Contractor to perform the Work as detailed in the Plans and these Special 24 Provisions, including removal, haul, and disposal of non-native material; removal, haul, 25 and disposal of existing modular block wall; grading the park area; furnishing, placing, 26 and compacting native material or common borrow meeting the requirements of Section 27 9-03.14(3) after removal of the existing modular block wall; furnishing all materials and 28 equipment necessary to complete the Work. 29 30 8-03.DOCX 31 Irrigation Symptoms 32 33 8-03.INST1.DOCX 34 Section 8-03 is replaced with the following: 35 36 8-03.SA1.DOCX 37 (******) 38 Description 39 This Work consists of installing a temporary irrigation system in accordance with these 40 Specifications and the details shown in the Plans or as approved by the Engineer. 41 42 Materials 43 Materials shall meet the requirements of Sections 9-15 and 9-29. 44 45 Construction Requirements 46 47