4. Activity Assignments and Designations: <br />a. Limit activities, where possible, excluding fabrication of materials and equipment, to <br />durations not longer than 20 days. Activities shall be definable and measurable. For <br />example, an activity described only as "Concrete" will likely be unacceptable. <br />b. Assign to each activity an appropriate, unique numerical designation and description. <br />c. Numerical designation shall incorporate the associated Specifications section number. <br />d. Activity description shall include sufficient detail to clearly communicate the intended <br />activity. Descriptions shall include identifiers for physical locations of work area or work <br />system, such as column lines, stationing, and elevations. Indicate unique description <br />for each activity. <br />e. Group deliveries of materials and equipment into a separate sub -schedule that is part <br />of the Progress Schedule. <br />f. Group construction into work area sub -schedules that are part of the Progress <br />Schedule by activity. <br />g. Clearly indicate, as activities separate from installation, necessary and required curing <br />periods. <br />5. Organization of Progress Schedules: <br />a. Indicate interfaces and dependencies with preceding, concurrent, and follow-on <br />activities, including those associated with the Work, other contractors at the Site, <br />Owner and the cellular tower company, and AWWD, Owner's consultants, authorities <br />having jurisdiction, and others as appropriate. Clearly indicate activities not under <br />Contractor's control. <br />b. Progress Schedules shall be CPM Progress Schedules. <br />c. Indicate on the separate Schedule of Submittals dates for submitting and reviewing <br />Shop Drawings, product data submittals, Samples, and other required submittals. <br />Coordinate Progress Schedule with the Schedule of Submittals. <br />d. Clearly indicate the critical path on the Progress Schedule. <br />B. Planned Work Schedule: <br />1. Within 30 days of the Effective Date of the Contract, indicate to Engineer the work days <br />and hours proposed by Contractor. Also indicate planned non -work days, such as <br />Contractor's holidays, weekends, etc. <br />2. Enforce subcontractors' and suppliers' when at the Site for compliance with Contractor's <br />work schedule accepted by the Engineer. <br />3. In the event of changes, submit to Engineer a revised work schedule. Furnish such <br />submittal not less than three days prior to changing Contractor's work schedule, except in <br />event of unanticipated emergency. <br />C. Preliminary Progress Schedule: <br />1. Within ten days after the Contract Times commence running, Contractor shall submit to <br />Engineer the preliminary Progress Schedule covering the entire Project, with associated <br />schedule -related submittals. <br />2. Submit preliminary Progress Schedule in its native (executable) format generated by the <br />scheduling software, transmitted in accordance with electronic communication protocols. <br />D. Initial Acceptance of Progress Schedule: <br />1. Not less than 10 days before submission of the first application for Payment, a scheduling <br />conference attended by Contractor, Progress Schedule preparer, Engineer, and others as <br />appropriate will be held at the Site to review for acceptability to Engineer the preliminary <br />Progress Schedule and associated schedule -related submittals. Following the scheduling <br />conference, Contractor shall have five days to make corrections and adjustments and to <br />complete and resubmit the Progress Schedule and associated schedule -related submittals. <br />Contractor will not be eligible for first progress payment until acceptable Progress Schedule <br />and associated schedule -related Submittals are submitted to and accepted by the <br />Engineer. <br />2. Submit acceptable Progress Schedule, together with associated schedule -related <br />submittals per Section 01 31 26 — Electronic Communication Protocols, and Section 01 33 <br />00 - Submittal Procedures. Also submit acceptable form of Progress Schedule in its native <br />Reservoir 3 Replacement Phase 1 <br />Work Order No. UP3739 01 32 16 <br />CONSTRUCTION PROGRESS SCHEDULE March 2024 <br />