City of Everett 01 26 00 - 1 <br /> <br /> <br />01 26 00 - 1 CONTRACT MODIFICATION PROCEDURES <br /> <br />SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES <br />PART 1 - GENERAL <br />1.1 SUMMARY OF MODIFICATIONS PROCEDURES <br />A. Changes to the Work may be required due to field conditions, requests made by the <br />Owner, clarifications to the bid documents, or other needs that result in a change in the <br />cost of the work and/or change in the number of contract days per 00 72 00-6. The <br />changes to the work will be tracked individually as Request for Change Proposals <br />(RFCP.). Request for Change Proposals may either be prepared as a Field Directive, or <br />as a request for pricing prior to proceeding with the work. <br />B. A change order will be issued for one or more RFCP’s grouped into a single change <br />order. Payment for changed work cannot be paid until the change order is finalized, and <br />approved as outlined per 00 72 00 6.3. <br />C. The Request for Change Proposal shall clearly identify all labor, material, equipment, <br />incidentals, including subcontractor’s and supplier’s invoices or quotes and Contractor’s <br />timecards. A reference from the latest approved schedule shall be attached justifying <br />any time extension request. Mark ups for all overhead, profit, bond cost, B & O taxes, <br />and insurance shall be added per 00 72 00. The form included at the end of this section <br />will be used for directing the work to be done in one of the two manners described below. <br />D. Contractor, and Subcontractors where required, shall provide a breakdown of labor costs <br />including basic wage rates, fringe benefits, FICA, FUTA and SUCA add-ons, per 00 72 <br />00 9.6. Where premium time is involved, the Contractor shall provide a breakdown of <br />costs in the same detail. <br />1.2 FIELD DIRECTIVE MODIFICATION PROPOSALS <br />A. Changed conditions and/or unanticipated circumstances may require immediate <br />revisions to Work which are essential and from which a delay would result in a time and <br />or cost penalty to the project. When such a condition exists, the Owner shall issue a <br />written Field Directive to the Contractor. <br />B. The Owner will provide direction for the Contractor identifying the necessary changes to <br />be made. The Field Directive shall be identified with a Request for Change number. The <br />Contractor will provide pricing per 1.01 C of this section within 15 days of the completion <br />of the work. <br />1.3 LUMP SUM MODIFICATION PROPOSALS <br />A. The Owner may request priced proposals which either add or delete work prior to <br />proceeding with any changes.