<br /> <br />City of Everett 01 32 16-1 June 2024 <br />WFP Air Scour Blower Building Replacement Issued for Bid <br />UP3813 <br />SECTION 01 32 16 <br />CONSTRUCTION PROGRESS SCHEDULE <br />PART 1 : GENERAL <br />1.01 CONSTRUCTION SCHEDULE <br />A. The Contractor shall prepare a construction schedule showing all tasks required <br />to perform the work. Schedule shall show all tasks performed by all trades that is <br />required to perform work within the contract time. The Schedule shall include <br />sufficient time for cleaning, punch list review, and completion of punch list items <br />prior to the designated physical completion date. <br />1.02 FORMAT <br />A. The Schedule shall be a critical path method Gantt chart style and follow the <br />Type B Progress Schedule in WSDOT Standard Specification Section <br />1-08.3(2)B. <br />B. The Schedule shall clearly identify all work and detailed to show specific steps to <br />perform work. The relationship between the work items shall show the starting <br />date, length of time required to perform work, completion of the work within the <br />time frame shown. <br />C. All work found on the schedule of values shall be clearly identified. Unless <br />otherwise expressly authorized in writing by the City’s representative, the <br />Contractor must integrate the schedules with the Schedule of Values and unit <br />price items so that each construction activity is represented by a dollar value. <br />D. Submittal dates shall be included and the relationship between submittal and the <br />work item shall be identified. <br />E. Materials requiring long lead times shall be clearly identified on the schedule. <br />This shall include: <br />1. Date materials musts be ordered. <br />2. Time for manufacturing. <br />3. Time for delivery. <br />4. Delivery date (expected date materials to be at the project). <br />5. Date of Installation. <br />1.03 SUBMITTAL <br />A. At the pre-construction meeting, a preliminary schedule is required to be <br />submitted. Once the preliminary schedule has been approved, the schedule shall <br />become the Project Schedule. The Project Schedule, as approved by the City, <br />will be an integral part of the contract and will establish interim completion dates <br />for the various activities under the contract. <br />B. Schedule shall be submitted electronically. Acceptable formats are .xls and pdf.