Commissioning Plan Page 19 <br /> 2. Provide plumbing submittals as specified in specifications. Revise as necessary <br /> per Cx team review comments. <br /> 3. Review design for provision of power connections to plumbing systems <br /> equipment and devices. <br /> 4. Provide Start-up plan to owner and CA for review. <br /> 5. Perform start-up and testing of plumbing equipment and systems with assistance <br /> by the manufacturer's Representative, as necessary. <br /> 6. Verify the completion of all start-up activities and document as required with <br /> start-up reports, flushing reports, pressure test reports, and applicable <br /> documentation as required to confirm completion of systems readiness for start <br /> of commissioning activities. <br /> 7. Review CA-provided blank pre-functional performance tests (PFPTs) and <br /> functional performance tests (FPTs) for accuracy and conformance to installed <br /> plumbing systems. Provide review comments for the CA to update PFPTs and <br /> FPTs as necessary for accurate test forms. <br /> 8. Provide typical installation inspections, to be completed by the plumbing <br /> contractor, including but not limited to the following: <br /> a) Installation of pumping and mixing equipment, devices, and water <br /> distribution. <br /> b) Installation of all controllers and panels. <br /> c) Installation of all cable and conduit systems, control sensors and devices. <br /> d) Startup and manufacture testing of water moving or conditioning equipment <br /> and water treatment systems. <br /> e) Programming of all controllers, panels, alarms, reports and data trends. <br /> 9. Include the cost of replacing pump impellers that may be required by TAB. <br /> 10. Provide temperature and pressure taps according to the Construction <br /> Documents for TAB and CX testing. <br /> 11. Document and submit executed pre-functional performance tests (PFPTs) 1 <br /> week minimum prior to scheduled functional performance testing (FPTs)with CA. <br /> 12. During startup, complete a full point-to-point test, sensor calibration and control <br /> system tests to ensure system is functioning correctly. Program and test all <br /> control sequences. Create and program all required schedules, alarms and <br /> reports. <br /> 13. Assist and cooperate with the TAB contractor in the following manner: <br /> a) Meet with the TAB contractor prior to beginning TAB and review the TAB <br /> plan to determine the capabilities of the control system toward completing <br /> TAB. Provide the TAB any needed unique instruments for setting terminal <br /> unit boxes and instruct TAB in their use. <br /> b) Provide a qualified technician to operate the controls to assist the TAB <br /> contractor in performing TAB, or provide sufficient training for TAB to <br /> operate the system without assistance. <br /> 14. Perform plumbing testing. Assist and be available on site for TAB activities. <br /> 15. Assist the CC with performance verification testing (PVT) of equipment and <br /> systems as defined in contract documents to confirm completion of systems <br /> readiness for start of commissioning activities. <br /> 16. Place equipment and systems into automatic operation and continuing the <br /> operation during each working day of CX process, as required. <br /> 17. Operate the equipment and system as required for Functional Performance <br /> Testing. Provide a qualified representative to assist the commissioning team in <br /> performing all tests including verification for sequence of operation, alarm <br /> Clare's Place Ventilation Revision <br /> AfNeudorfer Engineers, LLC. Page 19 of 68 Everett, WA <br />