Commissioning Plan Page 22 <br /> 16. Create and program all Graphic screens including testing functionality of all <br /> graphic screen control points and data points. Create and program all required <br /> schedules, alarms and reports. <br /> 17. Provide a calibration check out with a certification that the software and hardware <br /> check out is completed prior to the start of the Functional Performance Testing. <br /> 18. Calibrate all sensors and devices. Provide documentation of calibration using <br /> standard contractor or manufacture's form sensor and devices requiring <br /> calibration including but not limited to: <br /> a) Humidity/Temperature Sensors <br /> b) Differential Pressure Switches <br /> c) Duct Pressure Sensors <br /> d) Airflow Sensors <br /> 19. Place equipment and systems into automatic operation and continuing the <br /> operation during each working day of CX process, as required. <br /> 20. Operate the equipment and system as required for Functional Performance <br /> Testing. Provide a qualified representative to assist the commissioning team in <br /> performing all tests including verification for sequence of operation, alarm <br /> generation, shutdowns for local and remote annunciation, protective features, all <br /> normal and abnormal failure conditions. <br /> 21. Provide a qualified representative to assist the commissioning team in <br /> performing all tests including verification for sequence of operation, alarm <br /> generation, shutdowns for local and remote annunciation, protective features, all <br /> normal and abnormal failure conditions. <br /> 22. Assist and cooperate with the CA in the following manner: <br /> a) Provide a skilled programmer/technician who is familiar with this building to <br /> assist the CA to execute a complete commissioning point-to-point and <br /> sensor calibration verification of the controls system. This control system <br /> verification test is intended to verify all installation is complete, tested and <br /> ready for functional testing. <br /> b) Using a skilled technician who is familiar with the building systems, execute <br /> the functional testing as specified in the design documents and as to be <br /> witnessed and directed by the CA. <br /> c) Compile control system trend logs for each equipment controller and device <br /> integrated to the BAS. Trend logs shall be graphical format with labeled X- <br /> and Y-axis, minimum of 1 week duration. Excel and text file documents will <br /> not be accepted. <br /> 23. Participate in fine-tuning or troubleshooting of system performance if either <br /> measure became necessary. Coordinate with the CA and contractors to optimize <br /> system settings as practical during Functional Performance Testing. <br /> 24. Provide complete operation and maintenance information and `As-Built" drawings <br /> to the general contractor and CA for verification, organization and distribution. <br /> List and clearly identify the locations of all flow stations and pressure stations. <br /> 25. Provide a qualified technician to perform owner training for the BAS. <br /> K. TAB Contractor Responsibilities <br /> 1. Coordinate with the mechanical subcontractor, plumbing contractor, sheet metal <br /> contractor, and controls contractor. <br /> 2. Prepare a schedule for TAB activities. Update the schedule as appropriate and <br /> notify the CA ahead of time when commissioning activities are not yet performed <br /> or if scheduling will delay construction. <br /> Clare's Place Ventilation Revision <br /> IV Neudorfer Engineers, LLC. Page 22 of 68 Everett, WA <br />