To: City Of Everett Department Transit COP #: 03 <br />3201 Smith Avenue Suite 215 Everett WA 98201 Date:7/31/2024 <br />Eclipse Mill Park Inductive Charging Infrastructure Attn:Brad Chenaweth <br />Project:23-06-ECL Rev2 - 8/21/2024 <br />Description: <br />COP #3 is to safe the site during the methane gas testing pried . Valdez construction has include <br /> the following scopes to prepare the site to demob. <br />Fence rental, Labor/operator, Equipment, Mob-in fee for concrete sub, Mob-in fee for GC, <br />material cost disposal fee <br />Authored By: Peter Uzunov <br />Cost Breakdown: <br />Labor:Hours Rate Item Total <br />Project Manager 3 85.00$ 255.00$ <br />Superintendent 3 75.00$ 225.00$ <br />Operator 8 86.00$ 688.00$ <br />Labor 8 66.16$ 529.28$ <br />Material & Equipment: Qty. Cost Item Total <br />Concrete Remob Fee 1 2,000.00$ 2,000.00$ <br />GC Mob Fee 1 500.00$ 500.00$ <br />Fence Retal per month 14 30.00$ 420.00$ <br />CSBC 4 22.50$ 90.00$ <br />Rental equipment 1 320.00$ 320.00$ <br />Loader, Compactore, 8 85.00$ 680.00$ <br />Cost Summary:Amount: <br />Labor:1,697.28$ <br />Material & Equipment:4,010.00$ <br />Subtotal:5,707.28$ <br />Overhead:10.0%570.73$ <br />Profit:5%313.90$ <br />COP Total: 6,591.91$ <br />Total does not include WA State Sales Tax <br />Work will not proceed until this COP is included in an executed change order updating the contract price. <br />This COP:6,591.91$ <br />Other Pending COP's: <br />Total Pending COP's:6,591.91$ <br />Authorized Signature:Date: <br />Owner or Owner's Representative <br />Authorized Signature: Date: <br />Valdez Construction, Inc. <br />Change Order Proposal <br />Reservation of Rights. This change order proposal is based solely on direct cost elements such as labor, material, and normal markups, and does not include any <br />amount for changes in the sequence of work, delays, disruption, rescheduling, extended overhead impact costs which are not possible to assess at the present <br />time. Right is expressly reserved to make claim for any and all of these acceleration, and/or related items of compensable cost overrun prior to final settlement of <br />this Contract.