CITY OF EVERETT SPECIAL PROVISIONS
<br />
<br />LS 47 – Beverly Lake Sewer ReplacementDivision B – BID DESCRIPTIONS January 30, 2025
<br />WO No. – UP3529 SP - 7
<br />
<br />curb and gutter and sidewalk includes, but is not limited to, the saw-cutting necessary for the
<br />final joint between existing concrete sidewalk or curb and permanent concrete repair.
<br />Include cost of cleanup by vacuum collection and disposal of the cuttings slurry with this bid
<br />item as there will be no separate payment for cleanup.
<br />
<br />Measurement and payment for the SAWCUT CONCRETE CURB, GUTTER AND
<br />SIDEWALK shall be per Linear Foot (LF), complete.
<br />
<br />Bid Item 14 - PUMP STATION BELOW GRADE
<br />Measurement and Payment: Lump Sum (LS)
<br />The lump sum bid item for the pump station below grade shall be full compensation for all
<br />labor, material, incidentals, tools, and equipment necessary to satisfactorily complete the
<br />work as defined in the Standard Specifications, Standard Drawings, these Specifications,
<br />and as shown on the Contract Plans.
<br />
<br />The installation of the pump station structure below grade shall include, but is not limited to,
<br />the following: excavation, structural fill, hauling, forming, foundation, fabrication, erection,
<br />concrete, structural steel supports, “wye” vault with H-20, hatches, bar screen vault with H-
<br />20 hatches, bar screen assembly, wet well and access with H-20 hatches, concrete base
<br />slab, grout, fill, and other miscellaneous and appurtenant work.
<br />
<br />Measurement and payment for the pump station structure below grade shall be as a lump-
<br />sum item, complete.
<br />
<br />Bid Item 15 - PUMP STATION STRUCTURE ABOVE GRADE
<br />Measurement and Payment: Lump Sum
<br />The unit contract price for the pump station structure above grade by lump sum and shall be
<br />full compensation for all labor, material, incidentals, tools, and equipment necessary to
<br />satisfactorily complete the work as defined in the Standard Specifications, Standard
<br />Drawings, these Specifications, and as shown on the Contract Plans.
<br />
<br />The installation of the pump station structure above grade shall include, but is not limited to,
<br />the following: electrical shelter, electrical rack, framing, fabrication, erection, concrete , steel
<br />brackets, anchor bolts, reinforcement, steel roof, framing, flashing, roof sheeting, grating,
<br />shelter framing and supports, coatings, standby generator foundation/pad, transformer pad,
<br />site low voltage and electrical conduits and other miscellaneous and appurtenant work.
<br />
<br />Measurement and payment for the pump station structure above grade shall be as a lump-
<br />sum item, complete.
<br />.
<br />Bid Item 16 - SUBMERSIBLE PUMP ASSEMBLIES
<br />Measurement and Payment: Per Unit Price (EA)
<br />The unit contract price for the pump assemblies by (EA) and shall be full compensation for
<br />all labor, material, incidentals, tools, and equipment necessary to satisfactorily complete the
|