2025 PAVEMENT MAINTENANCE OVERLAY SPECIAL PROVISIONS <br />PW# 3830 <br /> SP-32 March 26, 2025 <br /> <br />1-08.3.GR1 1 <br />Progress Schedule 2 <br /> 3 <br />COE F1-08.3(2)A.RTF 4 <br />1-08.3(2)A Type A Progress Schedule 5 <br />(December 30, 2022 APWA GSP) 6 <br /> 7 <br />Revise this section to read: 8 <br /> 9 <br />The Contractor shall submit *** 3 *** copies of a Type A Progress Schedule no later than 10 <br />at the preconstruction conference, or some other mutually agreed upon submittal time. 11 <br />The schedule may be a critical path method (CPM) schedule, bar chart, or other standard 12 <br />schedule format. Regardless of which format used, the schedule shall identify the critical 13 <br />path. The Engineer will evaluate the Type A Progress Schedule and approve or return the 14 <br />schedule for corrections within 15 calendar days of receiving the submittal. 15 <br /> 16 <br />1-08.4.RTF 17 <br />1-08.4 Prosecution of Work 18 <br /> 19 <br />Delete this section and replace it with the following: 20 <br /> 21 <br />1-08.4 Notice to Proceed and Prosecution of Work 22 <br />(July 23, 2015 APWA GSP) 23 <br /> 24 <br />Notice to Proceed will be given after the contract has been executed and the contract 25 <br />bond and evidence of insurance have been approved and filed by the Contracting 26 <br />Agency. The Contractor shall not commence with the work until the Notice to Proceed 27 <br />has been given by the Engineer. The Contractor shall commence construction activities 28 <br />on the project site within ten days of the Notice to Proceed Date, unless otherwise 29 <br />approved in writing. The Contractor shall diligently pursue the work to the physical 30 <br />completion date within the time specified in the contract. Voluntary shutdown or slowing 31 <br />of operations by the Contractor shall not relieve the Contractor of the responsibility to 32 <br />complete the work within the time(s) specified in the contract. 33 <br /> 34 <br />When shown in the Plans, the first order of work shall be the installation of high visibility 35 <br />fencing to delineate all areas for protection or restoration, as described in the Contract. 36 <br />Installation of high visibility fencing adjacent to the roadway shall occur after the 37 <br />placement of all necessary signs and traffic control devices in accordance with 1-10.1(2). 38 <br />Upon construction of the fencing, the Contractor shall request the Engineer to inspect the 39 <br />fence. No other work shall be performed on the site until the Contracting Agency has 40 <br />accepted the installation of high visibility fencing, as described in the Contract. 41 <br /> 42 <br />1-08.5.GR1 43 <br />Time for Completion 44 <br /> 45 <br />1-08.5.INST2.GR1 46 <br />Section 1-08.5 is supplemented with the following: 47 <br /> 48 <br />F1-08.5.OPT7.FR1.docx 49 <br />(March 13, 1995) 50 <br /> 51