Laserfiche WebLink
2025 PAVEMENT MAINTENANCE OVERLAY SPECIAL PROVISIONS <br />PW# 3830 <br /> SP-73 March 26, 2025 <br /> <br />progress estimate end date. For work completed after all authorized 1 <br />working days are used, the adjustment will be based on the posted 2 <br />reference cost during which contract time was exhausted. 3 <br /> 4 <br /> Base Cost is selected from the website table based on the “Date 5 <br />Effective” that immediately precedes the contract bid opening date, and 6 <br />shall be a constant for all monthly adjustments. 7 <br /> 8 <br />Q = total tons of all classes of HMA paid in the current month’s progress 9 <br />payment. 10 <br /> 11 <br />“Asphalt Cost Price Adjustment”, by calculation. 12 <br />“Asphalt Cost Price Adjustment” will be calculated and paid for as described in this 13 <br />section. For the purpose of providing a common proposal for all bidders, the Contracting 14 <br />Agency has entered an amount in the proposal to become a part of the total bid by the 15 <br />Contractor. 16 <br /> 17 <br />END DIVISION5.RTF 18 <br /> 19 <br /> 20 <br />END DIVISION 5 21 <br /> 22