2025 FEDERAL OVERLAY, BROADWAY – CALIFORNIA ST TO 18TH ST SPECIAL PROVISIONS <br />FEDERAL AID# STBGUL-2715(012); COE PW# 3841 SP-18 May 6, 2025 <br /> <br />The Contractor will not be allowed an extension of contract time because of a delay in 1 <br />the performance of the work attributable to the exercise of the Engineer’s right 2 <br />hereunder. 3 <br /> 4 <br />Upon correction of all deficiencies, the Engineer will notify the Contractor and the 5 <br />Contracting Agency, in writing, of the date upon which the work was considered physically 6 <br />complete. That date shall constitute the Physical Completion Date of the contract, but shall 7 <br />not imply acceptance of the work or that all the obligations of the Contractor under the 8 <br />contract have been fulfilled. 9 <br /> 10 <br />1-05.11(3) Operational Testing 11 <br /> 12 <br />It is the intent of the Contracting Agency to have at the Physical Completion Date a 13 <br />complete and operable system. Therefore when the work involves the installation of 14 <br />machinery or other mechanical equipment; street lighting, electrical distribution or signal 15 <br />systems; irrigation systems; buildings; or other similar work it may be desirable for the 16 <br />Engineer to have the Contractor operate and test the work for a period of time after final 17 <br />inspection but prior to the physical completion date. Whenever items of work are listed in 18 <br />the Contract Provisions for operational testing they shall be fully tested under operating 19 <br />conditions for the time period specified to ensure their acceptability prior to the Physical 20 <br />Completion Date. During and following the test period, the Contractor shall correct any 21 <br />items of workmanship, materials, or equipment which prove faulty, or that are not in first 22 <br />class operating condition. Equipment, electrical controls, meters, or other devices and 23 <br />equipment to be tested during this period shall be tested under the observation of the 24 <br />Engineer, so that the Engineer may determine their suitability for the purpose for which 25 <br />they were installed. The Physical Completion Date cannot be established until testing 26 <br />and corrections have been completed to the satisfaction of the Engineer. 27 <br /> 28 <br />The costs for power, gas, labor, material, supplies, and everything else needed to 29 <br />successfully complete operational testing, shall be included in the unit contract prices 30 <br />related to the system being tested, unless specifically set forth otherwise in the proposal. 31 <br /> 32 <br />Operational and test periods, when required by the Engineer, shall not affect a 33 <br />manufacturer’s guaranties or warranties furnished under the terms of the contract. 34 <br /> 35 <br /> 36 <br />1-05.13.RTF 37 <br />1-05.13 Superintendents, Labor, and Equipment of Contractor 38 <br />(August 14, 2013 APWA GSP) 39 <br /> 40 <br />Delete the sixth and seventh paragraphs of this section. 41 <br /> 42 <br />1-05.14.GR1 43 <br />Cooperation with Other Contractors 44 <br /> 45 <br />1-05.14.INST1.GR1 46 <br />Section 1-05.14 is supplemented with the following: 47 <br /> 48