REFRIGERATION KEYNOTES REFRIGERATION SYMBOLS GENERAL NOTES
<br /> 10.12.1) .31 20
<br /> X## CIRCUIT NUMBER (CIRCUIT INFO) 1. PLANS INDICATE GENERAL ROUTING OF
<br /> 15.601 SLOPE REFRIGERANT LINES BACK TO XXX MODEL NUMBER REFRIGERANT LINES,WITH A SINGLE LINE
<br /> COMPRESSORS AT 1"PER 20'OF RUN.LOCATE SHOWN INDICATING BOTH SUCTION AND LIQUID
<br /> HIGHEST POINT OF REFRIGERATION LINES JUST CO IF CLEANOUTS(CO) LINE ROUTING FOR EACH SYSTEM.
<br /> BELOW BOTTOM CHORD OF JOIST OR BEAM. CONDENSATE DRAIN LINE(CD)
<br /> COORDINATE ELEVATION TO AVOID CONFLICTS 2. REFRIGERATION SYSTEM INSTALLATION SHALL
<br /> WITH DUCTWORK,LIGHTING,SKYLIGHTS,ETC. CONNECT TO EXISTING BE IN COMPLETE CONFORMANCE WITH
<br /> 15.602 SUPPORT HORIZONTAL RUNS OF REFRIGERANT �� CONTINUATION SPECIFICATIONS,AND WITH ALL REQUIREMENTS
<br /> LINES ON 1-5/8"X 1-5/8"UNISTRUT CHANNELS ON OF REFRIGERATION EQUIPMENT
<br /> MANUFACTURER.
<br /> MAXIMUM OF 6 FOOT CENTERS. DETAIL NUMBER
<br /> 15.603 AT ALL POINTS WHERE SUCTION LINES RISE, X# SHEET NUMBER (DETAIL REFERENCE) 3. REFRIGERATION DRAWINGS ARE PROVIDED AS
<br /> PROVIDE A SUCTION LINE TRAP AT THE BASE OF AN AID TO BIDDERS AND TO INDICATE DESIRED
<br /> THE RISER. ROUTING OF REFRIGERATION LINES;
<br /> 15.604 PROVIDE AIRTIGHT SEAL AROUND ALL PIPING EVAPORATOR COIL CONTRACTOR SHALL ASSUME FULL
<br /> AND BOLT PENETRATIONS THROUGH RESPONSIBILITY FOR CORRECT INSTALLATION
<br /> COOLER/FREEZER BOX WALLS OR CEILINGS. OF PIPING AND ACCESSORIES TO PROVIDE A
<br /> 15.605 SUPPORT EVAPORATORS WITH BOLTS THROUGH �§ ISOLATION VALVE COMPLETE AND FULLY OPERATING SYSTEM.
<br /> ROOF TO 1-5/8"X 1-5/8"X 10'LONG 14 GA.
<br /> GALVANIZED UNISTRUT SPANNING THREE ROOF ELBOW-TURNED DOWN 4. REFER TO SPECIFICATION 15600 FOR w %
<br /> PANELS.PROVIDE DOUBLE NUTS ON EACH BOLT. INSULATION THICKNESS.INSIDE DIAMETER OF
<br /> 15.606 CONDENSATE DRAIN;PITCH DRAIN LINES DOWN ELBOW TURNED UP INSULATION SHALL MATCH PIPE DIAMETER TO w w w g C u
<br /> APPROXIMATELY I/8"PER 12'TOWARD DRAIN. MINIMIZE AIR GAPS BETWEEN PIPING AND rc :gLLw:p000"
<br /> PROVIDE COPPER PIPING WITH ELECTRIC HEAT REFRIGERATION KEYNOTE REFERENCE INSULATION.PROVIDE FACTORY PRE- o a W..:
<br /> TAPE AND INSULATION ON ALL CONDENSATE REFRIGERATION PIPING(ABOVE) MANUFACTURED FITTINGS AT ALL TRAPS AND "O a ao�a o.oi-»rpa
<br /> LINES EXPOSED TO FREEZING TEMPERATURES. ELBOWS.WHERE PRE-MANUFACTURED z °���'o„„W,p 6 H o W o
<br /> ---------- REFRIGERATION PIPING(BELOW) FITTINGS ARE UNAVAILABLE MITER CUT ALL O 3«s�^=o��"+::�:
<br /> 15.607 SEE SCHEDULES FOR EVAPORATOR TYPES, F oe"��rcw-�Fpo�a
<br /> SIZES,AND CAPACITIES;CONTROL METHOD;AND ETR EXISTING TO REMAIN FITTINGS TO ENSURE PROPER SEAL BETWEEN6S
<br /> ALL REFRIGERATION PIPING SIZES,ETC. INSULATION SEGMENTS. o yw w o
<br /> lz
<br /> sa, oa� s
<br /> 15.608 END CONDENSATE LINE OVER RECEPTOR W/AIR (TYP) TYPICAL 5. PIPE INSULATION SHALL BE BLACK,UNLESS ai a �'�'�a:
<br /> GAP.CONTRACTOR SHALL ENSURE FLOOR DRAIN(S)AND DRAIN LINE OTHERWISE STATED ON PLANS OR
<br /> SERVING WALK-IN SPECIFICATIONS.
<br /> ARE FREE OF OBSTRUCTIONS AND FUNCTION 24 HOURS PRIOR TO SHUTTING DOWN ANY
<br /> PROPERLY.WHERE EXTENSIVE DAMAGE EXISTS REFRIGERATION SYSTEMS,HVAC SYSTEMS OR BUILDING 6. COORDINATE REFRIGERATION DEMOLITION
<br /> AND/OR PROPER DRAINAGE CANNOT BE AUTOMATION CONTROLS SYSTEMS,SEND EMAIL TO ISSUES WITH THE ARCHITECTURAL DRAWINGS.
<br /> OBTAINED COORDINATE WITH WALMART NSRM@WALMART.COM.THE E-MAIL SHALL STATE WHAT, REFER TO ARCHITECTURAL PLANS FOR
<br /> MECHANICAL CONSTRUCTION MANAGER. WHY,AND WHEN IT IS BEING SHUT DOWN AND HOW LONG REFRIGERATION EQUIPMENT DEMOLITION AND Z
<br /> 15.609 PROVIDE PVC DRAIN LINE FROM EACH CASE IT IS ANTICIPATED TO BE SHUT DOWN.THEN SEND A COOLER REPAIR AND REMODELING. ¢ HI
<br /> DRAIN CONNECTION SAME SIZE AS CASE FOLLOW UP EMAIL TO NSRM@WALMART.COM AFTER THE
<br /> OUTLET,AND END OVER FLOOR RECEPTOR WORK IS COMPLETE AND THE SYSTEM IS BACK UP AND 7, REFRIGERATION SYSTEM SHALL REMAIN Z o
<br /> W/AIR GAP;PITCH DRAINS 1/8"PER 12".PROVIDE RUNNING. OPERATIONAL DURING REMODELING.DURING F
<br /> DRAIN COVER GRATE TO MATCH EXISTING. THE PHASING OF OLD TO NEW SYSTEMS,BOTH Z
<br /> CONTRACTOR SHALL ENSURE RECEPTOR(S)AND REFERENCE ARCHITECTURAL DRAWINGS FOR ALL NEW NEW AND OLD REFRIGERATION SYSTEMS MAY
<br /> DRAIN LINE(S)SERVING CASE LINE-UP ARE FREE CASES BEING INSTALLED FOR CONNECTION LOCATION OF BE REQUIRED TO OPERATE AT THE SAME TIME j t]
<br /> OF OBSTRUCTIONS AND FUNCTION PROPERLY. UTILITIES.(TOP FED VS BOTTOM FED) FOR A SHORT PERIOD. z d
<br /> WHERE EXTENSIVE DAMAGE EXISTS AND/OR O
<br /> PROPER DRAINAGE CANNOT BE OBTAINED SEPARATE CONTRACTOR IS RESPONSIBLE FOR RE-SKIN 8. WHERE NEW REFRIGERATED EQUIPMENT IS U
<br /> COORDINATE WITH WALMART MECHANICAL OF EXISTING REFRIGERATED CASES TO REMAIN. INDICATED ON THE DRAWINGS,PROVIDE
<br /> CONSTRUCTION MANAGER. DEMOLITION,REMOVAL,AND TEMPORARY
<br /> 15.610 PROVIDE 0.020"PVC JACKET ON ALL ALL WORK ON THIS SHEET IS TO BE COMPLETED BY A STORAGE OF OLD EQUIPMENT PER WALMART
<br /> REFRIGERATION LINES EXTERIOR TO BUILDING. WALMART APPROVED CONTRACTOR. MECHANICAL SERVICES CONSTRUCTION
<br /> 15.617 COORDINATE REFRIGERATION LINE MANAGER'S INSTRUCTIONS,AND
<br /> PENETRATIONS THROUGH ROOF.REINFORCE REFRIGERATION CONTRACTOR IS RESPONSIBLE FOR ALL REFRIGERATION DEMO NOTES. O O
<br /> ROOF STRUCTURE AS NECESSARY.CUT ROOF FINAL REFRIGERATION ELECTRICAL TERMINATIONS TO z
<br /> OPENING FOR THE REFRIGERATION PIPE REFRIGERATION EQUIPMENT. 9. COORDINATE REMOVAL AND DISPOSAL OF O C\
<br /> PENETRATION AND SUPPLY ROOF CURB WITH EXISTING EVAPORATORS,REFRIGERATED O O Q
<br /> WEATHERTIGHT SHEETMETAL COVER. VERIFY EXACT LOCATION OF ALL REFRIGERATED CASES CASES,AND CONDENSING UNITS,WITH
<br /> PROPERLY FLASH,PATCH,AND REPAIR ROOF AS WITH FINAL MERCHANDISE PLAN. WALMART MECHANICAL SERVICES r~r� Q
<br /> REQUIRED FOR NEW PENETRATION. CONSTRUCTION MANAGER. Z J COORDINATE EXACT SIZE AND LOCATION OF COORDINATE LOCATION OF REFRIGERATED CASES WITH
<br /> ROOF PENETRATIONS WITH STRUCTURAL PLUMBING CONTRACTOR PRIOR TO CUTTING OF FLOOR 10. REMOVE COPPER LINES,EVAPORATORS,AND = Q 0
<br /> DRAWINGS. AND SETTING DRAINS. CONDENSATE LINES FROM COOLERS/ y <N a
<br /> �J
<br /> 15.621 REFRIGERATION CONTRACTOR SHALL RECEIVE, FREEZERS BEING REMOVED FROM SITE.
<br /> SET EQUIPMENT IN PLACE,LEVEL,AND START ALL EXISTING REFRIGERATED CASES ARE TO REMAIN COORDINATE WITH WALK-IN PANEL VENDOR U l
<br /> UP OWNER'S SELF-CONTAINED REFRIGERATED UNLESS NOTED OTHERWISE. FOR TIME LINE OF REPLACEMENT.REFERENCE > W z o
<br /> SPECIFICATION FOR CONTACT INFORMATION.
<br /> EQUIPMENT.INSTALLATION AND START-UP w w N
<br /> SHALL BE IN STRICT CONFORMANCE WITH THE IF REPLACED REFRIGERANT LINE SIZES ARE LARGER o
<br /> EQUIPMENT MANUFACTURER'S WRITTEN THAN SUCTION OR LIQUID HEADER STUB SIZES,REPLACE 11. WALK-IN PANEL VENDOR SHALL PROPERLY w Or ^'
<br /> INSTALLATION AND START-UP INSTRUCTIONS. STUB WITH SAME SIZE AS NEW REFRIGERANT LINE. PREPARE ALL COOLER/FREEZER PANELS, O W w
<br /> CONTRACTOR SHALL VERIFY CASE OPERATION COORDINATE WITH CONSTRUCTION MANAGER AND RACK GLASS DOORS,SLIDER OR SWING DOORS,
<br /> AND NOTIFY WALMART MECHANICAL OEM. PALLETIZE,AND PREPARE THE EQUIPMENT TO � o
<br /> CONSTRUCTION MANAGER IF EQUIPMENT IS NOT SHIP OFF SITE. m
<br /> OPERATING PROPERLY. CONTRACTOR TO RE-USE EXISTING CASE DRAINS. w
<br /> 12 COORDINATE WITH FIRE PROTECTION
<br /> 15.625 ROUTE REFRIGERATION LINES IN BASE OF CASE REPLACE DRAIN IF MORE THAN 1/2 OF DRAIN IS EXPOSED
<br /> TO SALES FLOOR.FIELD VERIFY EXACT LOCATIONS. CONTRACTOR FOR THE REMOVAL OF w
<br /> FOR ALL BOTTOM FED CONNECTED CASES. W
<br /> SPRINKLERS FOR ALL REMOVED ro
<br /> SLOPE BACK TO COMPRESSOR AT 1"PER 20'-0" j
<br /> OF RUN. PROJECT COORDINATED WITH REFRIGERATION VENDOR COOLER/FREEZER BOXES. Z
<br /> 15.635 REFRIGERATION CONTRACTOR SHALL INSTALL (OEM)AS INDICATED ON REFRIGERATION SCHEDULE(S). 13. COORDINATE WITH ELECTRICAL CONTRACTOR
<br /> REFRIGERATION MANUFACTURER-FURNISHED PRIOR TO INSTALLING ANY EQUIPMENT OR ADJUSTING FOR THE REMOVAL OF ALL REMOVED
<br /> LIQUID LINE SOLENOID VALVE AND EVAPORATOR PRESS RE REGULATOR IN A SERVICE RACK PARAMETERS,REFRIGERATION CONTRACTOR COOLER/FREEZER BOXES ELECTRICAL WIRING
<br /> ACCESSU .IBLE LOCATION INSIDE CASE DRAIN PAN SHALL REQUEST A SUCTION GROUP REPORT FOR ALL DEVICES.
<br /> CONTRACTOR SHALL FURNISH AND INSTALL RACKS AND SUCTION GROUPS WHERE WORK IS 14. COORDINATE WITH SAS CONTRACTOR FOR THE ISSUE BLOCK
<br /> FULL PORT ISOLATION BALL VALVE IN A SERVICE PERFORMED.REQUEST VIA EMAIL AT B.PTEAM1@WAL- REMOVAL OF ALL REMOVED COOLER/FREEZER
<br /> ACCESSIBLE LOCATION INSIDE CASE DRAIN PAN. MART.COM BOXES BAS WIRING AND DEVICES.
<br /> INSTALL CONTROL WIRING FROM VALVES BACK
<br /> TO CASE OR RACK CONTROLLER.REFER TO
<br /> REFRIGERATIONSUBMITTALS/SCHEDULES AND EPA CLEAN AIR ACT US 15. EXISTING REFRIGERATION PIPING MAY BE RE-
<br /> ED UNLESS OTHERWISE NOTED ON PLANS.
<br /> BAS PLANS FOR EXACT REQUIREMENTS.REFER REFER TO SCHEDULES FOR PIPE SIZE
<br /> TO SPECIFICATIONS FOR ASSET TAGGING REQUIREMENTS.
<br /> REQUIREMENTS. COMPLY WITH CLEAN AIR ACT,TITLE VI,SECTION 608
<br /> 15.636 REFRIGERATION CONTRACTOR SHALL INSTALL AND CODE OF FEDERAL REGULATION TITLE 40,PART 82 16. BUILDING COMPONENTS ABANDONED BY THE
<br /> REFRIGERATION MANUFACTURER-FURNISHED WHEN ADDING OR REMOVING REFRIGERATED SCOPE OF WORK SHALL BE SECURED TO
<br /> LIQUID LINE SOLENOID VALVE AND EVAPORATOR EQUIPMENT.RECORD ALL EQUIPMENT IDENTIFICATION PREVENT FALLING,LOOSENING,OR CREATING
<br /> PRESSURE REGULATOR IN A SERVICE NUMBERS,MODEL AND SERIAL NUMBERS,THE AMOUNT DAMAGE OF ANY KIND IN THE FUTURE.
<br /> ACCESSIBLE LOCATION ON TOP OF WALK-IN OF REFRIGERANT RECOVERED FROM EACH UNIT,THE
<br /> BOX.CONTRACTOR SHALL FURNISH AND DATE OF DECOMMISSIONING,COMPANY NAME AND 17. IF ANY RACK SYSTEMS WILL BE OPENED TO ADD
<br /> INSTALL FULL PORT ISOLATION BALL VALVE IN A SIGNATURE OF ON-SITE SUPERVISOR. OR REPLACE CASES,EVAPORATORS,ETC.THEN
<br /> SERVICE ACCESSIBLE LOCATION ON TOP OF 24 TO 48 HOURS AFTER THE WORK IS
<br /> WALK-IN BOX.INSTALL CONTROL WIRING FROM COMPLETED AND ALL FINAL ADJUSTMENTS
<br /> VALVES BACK TO CASE CONTROLLER OR HAVE BEEN MADE,PROVIDE AND CHANGE
<br /> CONDENSING UNIT.REFER TO REFRIGERATION LIQUID LINE FILTER CORES,OIL SYSTEM FILTER
<br /> SUBMITTALS/SCHEDULES AND BAS PLANS FOR USING SPORLAN OF STYLE FILTER,AND
<br /> EXACT REQUIREMENTS.REFER TO REPLACE SUCTION FILTERS.FILTERS ARE TO BE
<br /> SPECIFICATIONS FOR ASSET TAGGING RATED FOR WAX REMOVAL.CONTRACTOR TO
<br /> REQUIREMENTS. PROPERLY DISPOSE OF OIL AND COMPONENTS
<br /> REPLACED.REFER TO SPECIFICATION 15600.
<br /> 18. REFER TO GROCERY ARCHITECTURAL CHECKED BY. DL
<br /> DRAWINGS FOR ADDITIONAL WORK BY
<br /> REFRIGERATION CONTRACTOR. DRAWN BY: GM
<br /> 19. INSTALL ASSET TAGS ON ALL NEW PROTO: 90
<br /> PIPING SCHEDULE RACK MTC REFRIGERATED CASES AND COMPLETE THE
<br /> VERTICAL ESTIMATED DATA COLLECTION INFORMATION.DELETE PROTO CYCLE: 11/11/22
<br /> DEMOED ASSETS FROM ASSET TAGGING
<br /> PIPE HORIZONTAL SUCTION RISER TOTAL APPLICATION.REFER TO SPECIFICATIONS. DOCUMENT DATE: 02/22/23
<br /> DESIGNATION SUCTION AS REQUIRED LIQUID LENGTH"
<br /> 1C 31/8 15/8&25/8 15/8 16 20. UPON START-UP OF ALL NEW REFRIGERATED
<br /> 1.1C 15/8 1 5/8' 7/8 22 EQUIPMENT,CONSTRUCTION MANAGER SHALL
<br /> C01 1 1/8 7/8 112 38 REQUEST THE BUILDING PERFORMANCE
<br /> REPORT FOR ALL RACKS AND SUCTION GROUPS
<br /> 1.12C 13/8 1 3/8' 5/8 15 WHERE WORK IS PERFORMED.ANY DEVIATIONS
<br /> 1 2 3 CO2 7/8 5/8 1/2 31 NOTED ON THE REPORT MUST BE CORRECTED
<br /> 1.13C 13/8 1 1/8' 5/8 33 PRIOR TO PROJECT CLOSE OUT.REQUEST VIA
<br /> CO3 7/8 5/8 1/2 19 EMAIL AT B.PTEAM10WAL-MART.COM
<br /> C04 11/8 11/8 112 45
<br /> 12 13 1.2C 31/8 31/8' 13/8 13 FOOD PREP AREA NOTES
<br /> 1.21 C 15/8 1 5/8' 718 5
<br /> 1.22C 13/8 13/8 7/8 22
<br /> to 5/8 5/8 1/2 49 ❑ ROUTE ALL PIPING CONCEALED WITHIN STUD
<br /> C06 1 1/8 7/8 1/2 27 ❑ WALLS WHEREVER POSSIBLE.
<br /> 2.❑ ALL EXPOSED PIPE INSULATION SHALL BE
<br /> 1 15.604 4 C16 1 1/8 7/8 1/2 51 ❑ CLAD PER SPECIFICATIONS.EXPOSED
<br /> 3 6 15.605 C07 5/8 5/8 1/2 17 ❑ PIPING SHALL COMPLY WITH ONE OF THE
<br /> 15.607 R3 ® 1.3C 25/8 25/8' 11/8 26 ❑ FOLLOWING INSTALLATION OPTIONS.
<br /> RCU 1&2 MOUNTED ON ROOF. R3 R3 RGO_ A.SURFACE MOUNTING PIPING WITH
<br /> REFER TO STRUCTURAL AND 8 \ C08 5/8 5/8 1/2 46
<br /> OEM SUBMITTALS FOR SUPPORT. R3 15.603 KRD44E-148TDAK NON-CORROSIVE ANCHORS;SEAL
<br /> 1.4C 2 5/8 2 5/8' 1118 28
<br /> ALL EMERSON CONDENSING TYp (NEW) 15.604 4 1.41C 718 5/8• 112 7 BOTH SIDES L PIPE S SURFACE
<br /> UNITS SUPPLIED WITH OWNER- 15.610 15,605 CONTINUOUSLY WITH SEALANT.
<br /> �Q-� 15.607 R3 C09 5/8 1/2 12 34 B.INSTALL PIPING 1/2"OFF FACE OF
<br /> 15.609 FURNISHED,CONTRACTOR- TYP P FREEZER R -1 C10 5/8 5/8 1/2 37 SURFACE TO ALLOW FOR CLEANING.
<br /> INSTALLED WIND SCREEN.TYP.
<br /> 15.625 USE ONLY NON-CORROSIVE
<br /> NEW MT S/C CASE KRD44E 48TDAK L 1.5C 25/8 21/8' 1118 16
<br /> 15.635 MATERIALS FOR ANCHORS AND❑
<br /> 15C-05 .621 w - (N W) 1.51C 15/8 7/8&11/8 7/8 34 SPACERS.
<br /> MTUMD j -� C71 13/8 11/8' 1/2 34
<br /> C.COVER PIPING WITH 20 GAUGE
<br /> 15.636
<br /> L - (REPLACEDI CO TYP C12 13/8 1 1/8• 5/8 71 STAINLESS STEEL BENT PLATES
<br /> 1 NEW PIPE CHASE IN tRCU-1 TYP ��� 1.6C 21/8 1 5/8" 7/8 44 MOUNTED TO SURFACE WITH NON-
<br /> ROOF.COORDINATE CORROSIVE ANCHORS;APPLY
<br /> R3 7 1.61C 15/8 13/8" 7/8 6
<br /> SIZE AND LOCATION 15.606 CONTINUOUS SEALANT ALONG EDGES
<br /> E15.617 WITH STRUCTURE(TYP) " - -- ryp R3 C13 1 1/8 1 1/8 1/2 25
<br /> J j AND JOINTS.
<br /> U I C14 13/8 11/8 5/8 �14
<br /> NEW HOT CASE D - 2 - REFRIGERATION - - .O�Tc rnNDENSATE - C15 L-1 7/8 1/2 3.❑ PROPER INSTALLATION OF SEALANTS IS
<br /> R3 PIPING DOWN LINE 17�0 PUMP MOUNTED C15a 1/8 5/8 11 ❑ CRITICAL TO MEETING WALMART QUALITY
<br /> - - - - - eTHROUGH ROOF.(TYP) ON FF�EEZER WALL 15.608
<br /> V J C156 7/8 5/8 1/2 ❑ STANDARDS.PROVIDE SEALANTS IN DOCUMENTS THAT DO NOT
<br /> \ RCU-3 MOUNTED ON ROOF. ❑ ACCORDANCE WITH DRAWINGS AND HAVE THE ARCHITECT OR
<br /> 1.2C ❑ SPECIFICATIONS.REFERENCE SECTION 07900 ENGINEER OF RECORD
<br /> REFER TO STRUCTURAL AND RISER SIZE IS SHOWN EVEN WHERE A RISER IS NOT EXPECTED.THIS IS FOR ❑ FOR SEALANT SCHEDULE. SEAL AND SIGNATURE
<br /> H \ ro OEM SUBMITTALS FOR SUPPORT. RCU- REFERENCE ONLY AND TO BE USED IN THE EVENT THAT A PIPING CONFLICT
<br /> lul 1.21C 4.❑ INTERIOR SEALANTS USED IN FOOD PREP SHALL BE CONSIDERED
<br /> 1J'C16 GLD66D 268TDAA CAUSES THE NEED FOR A RISER.IF RISER LENGTH EXCEEDS 4 FEET,IT MUST BE ❑ AREAS
<br /> OF SHALL MEET THE REQUIREMENTS FOR NOT FOR CONSTRUCTION
<br /> S COORDINATE ROUTINGTT 7 _ IN W) APPROVED BY ENGINEER OF RECORD. ❑ USE IN USDA REGULATED FACILITIES.
<br /> REFRIGERATION 15.604
<br /> `03 C05 R3 4 5.❑ PROVIDE CONTINUOUS USDA APPROVED
<br /> PIPING WITH EXISTING PICKUP COOLER 1 15.605 ❑ SEALANT AT ALL JOINTS BETWEEN MATERIALS
<br /> PIPING,DUCTWORK,AND 15.607 R3 THIS IS
<br /> TOTAL LENGTH INCLUDES HORIZONTAL AND VERTICAL PIPE SECTIONS. ❑ ON WALLS IN FOOD PREPARATION COOLER
<br /> 15.602 LIGHTS.(TYP) THIS IS ONLY AN ESTIMATE AND ACTUAL LENGTH WILL VARY. ❑ AND FREEZER AREAS. REFRIGERATION
<br /> f� 6.❑ ALL JOINTS BETWEEN DISSIMILAR MATERIALS PLANS
<br /> GT EXISTING 'TM'NEW PIPING ❑ SHALL BE SEALED AS REQUIRED FOR A
<br /> e RACK MTC HCR DOOR FURNISHED ❑ COMPLETE AND PROPER INSTALLATION,
<br /> AND INSTALLED BY ❑ REGARDLESS OF WHETHER SHOWN ON
<br /> MECH#1 OTHERS.TYP. ❑ DRAWINGS OR NOT.
<br /> A - T - - - - - - - - - - -
<br /> EXISTING CONDITIONS WERE TAKEN FROM EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
<br /> ORIGINFRONT REFRIGERATION PLAN PICKUP REFRIGERATION PLAN SEXACTALDRAWINGSANDMAY NOT REFLECT ATHOROUGONS INT THEIR
<br /> REL OF ATELL D FIELD.THE FAILURE
<br /> EXACT"AS-BUILT'CONDITIONS.CONTRACTOR SPECIFICATIONS IN THEIR RELATED FIELD.THE FAILURE
<br /> •1 SHALL FIELD VERIFY ALL EXISTING CONDITIONS TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
<br /> PRIOR TO SUBMITTING FINAL BIDS.CONTRACTOR NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
<br /> SHALL CAREFULLY COORDINATE NEW WORK AND THE WORK PROPERLY.NO ADDITIONAL SHEET:
<br /> DEMOLITION WITH ALL OTHER DISCIPLINES AND COMPENSATION SHALL BE ALLOWED BECAUSE OF R 1
<br /> EXISTING CONDITIONS. CONDITIONS THAT OCCUR DUE TO FAILURE TO
<br /> FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.