Exhibit A <br />New Item No. 104: Lauren Connection Underground Conditions Impact. Add new Lump <br />Sum item No. 104 entitled “Lauren Connection Underground Conditions Impact” in the Lump <br />Sum amount of $57,038.87 resulting in an increase to the contract of $57,038.87. <br />Justification for creating New Item No. 104 <br />This item will be used to compensate the contractor for impacts due to unforeseen underground <br />conditions encountered while performing time and operational sensitive transmission line work. <br />New Item No. 105: Valve Leakage Impacts. Add new Lump Sum item No. 105 entitled “Valve <br />Leakage Impacts” in the Lump Sum amount of $79,933.21 resulting in an increase to the <br />contract of $79,933.21. <br />Justification for creating New Item No. 105 <br />This item will be used to compensate the contractor for impacts due to unforeseen valve leakage <br />encountered while performing time and operational sensitive transmission line work. <br />New Item No. 106: Surge Line Alignment and Sequencing Revision. Add new Lump Sum <br />item No. 106 entitled “Surge Line Alignment and Sequencing Revision” in the Lump Sum <br />amount of $143,541.43 resulting in an increase to the contract of $143,541.43. <br />Justification for creating New Item No. 106 <br />This item will be used to compensate the contractor for impacts due to unforeseen alignment and <br />sequence conflicts discovered while preparing for time and operational sensitive transmission line <br />work. <br />New Item No. 107: Chlorination Building Drain Line Upgrade. Add new Lump Sum item No. <br />107 entitled “Chlorination Building Drain Line Upgrade” in the Lump Sum amount of $20,710.21 <br />resulting in an increase to the contract of $20,710.21. <br />Justification for creating New Item No. 107 <br />This item will be used to compensate the contractor for upgrading to current standard an outdated <br />and non-functioning drain line from the Chlorination Building. <br />New Item No. 108: Berry Line addition Depth. Add new Lump Sum item No. 108 entitled <br />“Berry Line Additional Depth” in the Lump Sum amount of $27,058.41 resulting in an increase to <br />the contract of $27,058.41. <br />Justification for creating New Item No. 108 <br />This item will be used to compensate the contractor for impacts due to unforeseen additional <br />depth encountered while performing time and operational sensitive transmission line work. <br />New Item No. 109: Flowmeter Vault HVAC Safety System. Add new Lump Sum item No. 109 <br />entitled “Flowmeter Vault HVAC Safety System” in the Lump Sum amount of $40,855.49 <br />resulting in an increase to the contract of $40,855.49.