Laserfiche WebLink
CITY OF EVERETT BID SET <br />EVERETT STATION HVAC AND CONTROLS IMPROVEMENTS <br />PROJECT NO. 24-3201 <br /> <br />01 32 16 -1 CONSTRUCTION PROGRESS SCHEDULE <br /> <br />GENERAL <br />1.01 CONSTRUCTION SCHEDULE <br /> The Contractor shall prepare a construction schedule showing all tasks required to perform the work. <br />Schedule shall show all tasks performed by all trades that is required to perform work within the contract <br />time. The Schedule shall include sufficient time for cleaning, punch list review and completion of punch list <br />items prior to the designated physical completion date. <br />1.02 FORMAT <br /> The Schedule shall be a critical path method Gantt chart style, preferably Microsoft Project. <br /> The Schedule shall clearly identify all work and detailed to show specific steps to perform work. The <br />relationship between the work items shall show the starting date, length of time required to perform work, <br />completion of the work within the time frame shown. <br /> All work found on the schedule of values shall be clearly identified. Unless otherwise expressly authorized in <br />writing by the Owner’s representative, the Contractor must integrate the schedules with the Schedule of <br />Values and unit price items so that each construction activity is represented by a dollar value. <br /> Submittals dates shall be included and the relationship between submittal and the work item shall be <br />identified <br /> Materials requiring long lead times shall be clearly identified on the schedule. This shall include: <br /> Date materials musts be ordered <br /> Time for manufacturing <br /> Time for delivery <br /> Delivery date (expected date materials to be at the project) <br /> Date of Installation <br />1.03 SUBMITTAL <br /> At the pre-construction meeting, a preliminary schedule is required to be submitted. Once the preliminary <br />schedule has been approved, the schedule shall become the Project Schedule. The Project Schedule, as <br />approved by the Owner, will be an integral part of the contract and will establish interim completion dates <br />for the various activities under the contract. <br /> Schedule shall be submitted electronic. Acceptable format .mmp or as otherwise approved by Owner. <br /> Review by the Owner or Owner’s Representative shall not constitute approval or acceptance of the <br />Contractor's construction means, methods, sequencing, logic, order, precedence and succession of activities <br />or Contractor’s ability to complete the Work in a timely manner. <br /> The review/approval of any schedule shall not transfer any of the Contractor’s responsibilities to the Owner. <br /> Subcontractors shall review all schedules prior to submittal. At the Owner’s option and sole discretion, Owner <br />may require Contractor to obtain written acceptance of each schedule by subcontractors as practical and <br />feasible, as the schedule relates to subcontractors’ work.