City of Everett 01 32 16 - 2 <br />PGSF WMVD Storm and Combined Sewer - Construction Package 2 WO# UP-3815-02 <br />01 32 16 - 2 CONSTRUCTION PROGRESS SCHEDULES AND REPORTS <br />B. Draft Project Schedule: <br />1. The initial Critical Path Method schedule (CPM) for the Contractors work that <br />includes the early start/finish and late start/finish dates for each contract activity, <br />milestone, constraint, significant contract activities and procurement of critical <br />materials specified in Division 1 through Division 40. <br />C. Baseline Schedule: <br />1. Includes revisions from the review comments of the Draft Project Schedule <br />submittal. <br />2. A CPM schedule that includes the Contractor’s complete plan and all the necessary <br />activities to perform the Contract work within the Contract Time including milestones <br />and constraints defined in the Contract. <br />D. Monthly Update Schedule: <br />1. Updates to the Baseline Schedule show the current construction schedule that <br />reflects actual progress to date, updating all changes to the Contract, and the <br />schedule plan to complete the work within the Contract Time. <br />E. Three Week Look-Ahead Schedule: <br />1. A three-week detailed look at work activities planned for this Period. Scope of detail <br />is to review the past week of progress and the future three weeks of planned work <br />activities. <br />2. Provide this schedule with greater detail than the CPM and prepare it in a format <br />that includes references to appropriate CPM schedule activity numbers and work <br />breakdown. <br />3. The three-week look-ahead schedule shall coordinate with the Monthly Update <br />Schedule. <br /> <br />1.3 SUBMITTALS <br />A. Procedures: Specification Section 01 33 00 Submittal Procedures. <br />B. Qualifications: Submit within fourteen (14) days after the effective date of the Notice to <br />Proceed. <br />C. Schedules: <br />1. Submit all schedules in accessible electronic data files in the software format in <br />which it was created and in PDF format. At a minimum, the data files shall provide <br />the CPM Network Diagram; tabular report listing of each activity by Early Start and <br />Total Float sorts; logic tie report providing the predecessor and successor for each <br />activity; precedence diagram; and earned value projections. <br />2. Draft Project Schedule: Submit within 45 days of NTP. This submittal will be <br />reviewed by the City’s Construction Manager as required in Specification Section 01 <br />33 00 Submittal Procedures to verify that the requirements of Specification Section <br />01 32 16 Construction Progress Schedules and Reports have been met and may <br />require more than one submission by the Contractor to attain a Review Action of 1 <br />(No Exceptions Taken) or 2 (Note Markings). When the Draft Project schedule