Laserfiche WebLink
Mr. Andy West <br />February 12, 2026 <br />Page 4 <br /> <br /> <br /> <br />profiles for routing power and communication duct banks for construction based on <br />design by the electrical engineer (Coffman or utility purveyor). Information provided to <br />KPFF will include the number and size of conduits and vaults and a schematic layout <br />plan. Profile will not occur until the CD phase. <br />• Coffman will identify loads for power and communications for the proposed buildings and <br />make an application to SnoPUD and communications purveyors. <br />• SnoPUD will design, permit, and construct the transmission line reroute. SnoPUD will <br />coordinate with the design-build team for size and location of new power poles to ensure <br />the stadium meets setback requirements. <br />• The City of Everett will design and prepare all construction documents for traffic signal <br />modifications as required to serve this project. <br />• The City of Everett will be able to obtain all the required parcels as identified in Phase <br />1A deliverable including Parcel 26. <br />• Project illumination engineer will prepare: <br />o A site lighting layout and coordinate layout and associated electrical loads with <br />SnoPUD for power feed. <br />o Illumination calculations for approval by the City. <br />o Light pole layout for KPFF for use in civil drawings for coordination with site utilities. <br />• DLR will design and document all grading over and within the structure. KPFF will <br />document grading outside the stadium structure. <br />• KPFF will design and document all vehicular and pedestrian pavement sections with input <br />from the geotechnical engineer. Any specialty finish or jointing will be by Walker Macy. <br />• Walker Macy will take the lead on grading for the two main entrances (Wall Street and <br />Pacific Avenue) during DD. Grading scope at the main entrances will be transferred to <br />KPFF after DD for permit and construction documents. <br />• DA Hogan will design and document all elements of the proposed sports field including <br />material, grading, striping, and drainage. <br />• The proposed development will not result in an increase to the existing impervious <br />surface area; therefore, flow control is not required. <br />• Water quality treatment will not be required because the site discharges to a combined <br />sewer system. <br />• KPFF will not be providing a Revit BIM model of site improvements or utilities. KPFF will <br />provide a digital terrain model of the site grading and utility profiles in Civil3D for <br />inclusion into the project BIM model. <br />• Structural design for site walls, planters, light pole bases, and vaults is by DLR structural team. <br />• A Stormwater Pollution Prevention Plan (SWPPP) and coverage under the DOE <br />CSWGP is not required for this site because it discharges to a combined sewer. <br />Progressive Design-Build Contract for Everett Outdoor Event Center <br />Exhibit to Amendment No. 1 - Phase 1B Work and Fee Proposal