Project: Shore Avenue Storm Water Outfall Improvements Project
<br /> Change Order No.2
<br /> Change Order Effective Date: May 11, 2016
<br /> Modify existing bid item #60 titled, "Crushed Surfacing Top Course," by deleting 350 tons of
<br /> crushed surfacing top course, at the unit price of$35.00 per ton, resulting in a$12,250.00 deduct from
<br /> the contract price.
<br /> Modify existing bid item #61 titled, "Crushed Surfacing Base Course," by adding 440 tons of
<br /> crushed surfacing base course, at the unit price of$38.00 per ton, resulting in a$16,720.00 contract
<br /> price increase.
<br /> Modify existing bid item #62 titled, "HMA Class 'A-inch PG 64-22," by adding 70 tons of HMA
<br /> Class 1/2-inch PG 64-22, at the unit contract price of$102.50 per ton, resulting in a $7,175.00 increase
<br /> to the contract price.
<br /> Modify existing bid item #63 titled, "Planing Bituminous Pavement," by deleting 2,530.00 square
<br /> yards of planing bituminous pavement, at the unit price of$3.50 per square yard, resulting in a
<br /> $8,222.50 decrease to the contract price.
<br /> Modify existing bid item #64 titled, "Temporary Pavement Patch," by deleting 1,000 square yards
<br /> of temporary pavement patch, at the unit price of$70.50 per square yard, resulting in a $70,500.00
<br /> deduct from the contract price.
<br /> Modify existing bid item #76,titled, "Gravel Borrow Including Haul," by adding an additional
<br /> 2,100 tons of gravel borrow including haul, at the unit price of$21.00 per ton, resulting in a
<br /> $44,100.00 contract price increase.
<br /> Modify existing bid item #77 titled, "Gravel Backfill for Foundations Class A," by deleting 100
<br /> tons of gravel backfill for foundations class A, at the unit price of$35.00 per ton, resulting in a
<br /> $3,500.00 deduct from the contract price.
<br /> Modify existing bid item #79 titled, "Cleanout," by deleting 1 each cleanout, at the unit price of
<br /> $2,400.00, resulting in a $2,400.00 deduct from the contract price.
<br /> Modify existing bid item #82 titled, "Extruded Cement Concrete Curb," by deleting 190.00 linear
<br /> feet of extruded cement concrete curb, at the unit contract price of$38.00 per linear foot, resulting in a
<br /> $7,220.00 deduct from the contract.
<br /> Modifications made to the above twelve (12) items results in a $51,187.50 contract price decrease to
<br /> schedule B.
<br /> New items being added to schedule B are as follows:
<br /> Add new item #201 to schedule B titled, "Costs for Initial Changed Conditions Notice", in the lump
<br /> sum amount of$84,995.54.
<br /> Add new item #202 to schedule B titled, "Additional Restoration Work, Lot 4 to 33rd Ave. W.", in
<br /> the lump sum amount of$53,900.00.
<br /> Page 4 of 7
<br />
|