CITY OF EVERETT SPECIAL PROVISIONS 1 <br /> BID ITEM A-3 & B-3: MOBILIZATION , <br /> Measurement and Payment: Lump Sum <br /> The lump sum bid for mobilization shall constitute full compensation for all preconstruction costs U <br /> of preparatory work and operations performed by the Contractor, including, but not limited to, <br /> those necessary for the movement of his personnel, equipment, supplies and incidentals to the <br /> project site; for the establishment of offices, buildings and other facilities necessary for work on <br /> this project; for premiums on bonds and insurance for the project, and for work and operations <br /> which must be performed or costs incurred before beginning production work on the various <br /> items on the project site. Mobilization also includes, but is not limited to: posting construction <br /> identification signs, securing permits, establishing safety and security measures, submitting the <br /> project schedule, providing product/materials submittals, and providing assistance to <br /> business/institution owners and managers and/or affected residents to minimize and mitigate <br /> impacts during construction (including but not limited to; mail and package delivery, garbage <br /> and recycling pickup, freight delivery, handicap parking and access, customer/patient access <br /> and parking etc). Mobilization costs for all subcontracted work shall be considered to be <br /> included. This lump sum bid item includes all costs for utility coordination as noted in the plans <br /> and specifications. <br /> Items which are not included in this item include, but are not limited to: I <br /> (a) Any portion of the work covered by a specific bid item or incidental work which is to be <br /> included in a bid item or items. <br /> (b) Profit, interest on borrowed money, overhead or management costs. <br /> Partial payments will be made for the lump sum contract price for "Mobilization" as follows: <br /> When 5% of the total original contract amount is earned from other bid items, 50% of the <br /> amount bid for mobilization, or 5% of the total original contract amount, whichever is the least, <br /> will be paid. <br /> When 10% of the total original contract amount is earned from other bid items. 100% of the I <br /> amount bid for mobilization, or 10% of the total contract amount, whichever is the least, will be <br /> paid. <br /> Upon completion of all work on the project, payment of any amount bid for mobilization in <br /> excess of 10% of the total original contract amount will be paid. <br /> BID ITEM A-4 & B-4: TRAFFIC CONTROL LABOR I <br /> Measurement and Payment: Unit Price per Hour <br /> This unit price bid item includes full compensation for traffic control labor as identified in <br /> Sectionl-10.3(4) of the Special Provisions. The Contractor shall furnish all personnel for <br /> flagging to control traffic, including pedestrians, during construction operations in accordance <br /> with Section 1-10 of the Standard Specifications, the drawings, approved traffic control plans, as <br /> directed by the City and these Special Provisions. <br /> Measurement for traffic control labor shall be the total number of hours performed by all i <br /> personnel, verified and documented by the City's Inspector. <br /> I <br /> SEWER SYSTEM REPLACEMENT AND CAPACITY IMPROVEMENTS SEWER "M" PHASE II <br /> WO No.- UP3470-10 Division D-BID ITEM DESCRIPTIONS April 2016 <br /> SP -32 <br />