I <br /> CITY OF EVERETT PUBLIC WORKS DOCUMENT 00 72 13 <br /> SPECIAL PROVISIONS GENERAL CONDITIONS <br /> the option of doing such work with its own force at the Contractor's expense, or <br /> permitting the work to be performed by the Contractor. <br /> 4. Unknown Utilities <br /> a. When a utility interferes with the Work and is either(1) not identified on the Drawings <br /> or(2) located in a position significantly different from that specified on the Drawings, <br /> Contractor shall follow the procedures of ARTICLE 11. DIFFERING SITE <br /> CONDITIONS. Interference with the Work is defined as a utility that crosses or <br /> projects into the plane of the Work at an elevation between the top and bottom of the <br /> Work. If it is necessary to remove, relocate, or temporarily maintain the utility, that <br /> work shall be included in a Change Order. The utility owner has the option of doing <br /> such work or permitting the work to be performed by the Contractor. In either case,the <br /> cost of the work incurred by or charged to the Contractor will be included in a Change <br /> Order. <br /> 2.4 Submittals <br /> A. Where required by the Contract Documents, the Contractor shall submit information which will <br /> enable the Owner's Representative to advise the Owner whether the Contractor's proposed <br /> materials,Equipment or methods of work are in general conformance to the design concept and in <br /> compliance with the Drawings and Specifications, such as catalog cuts and shop, working or <br /> detail drawings. In its Submittals, the Contractor shall expressly and explicitly notify the <br /> Owner's Representative of any and all deviations from the Specifications. Without express and <br /> explicit Notice of a deviation from the Contract requirements, approval of a Submittal does not <br /> relieve Contractor from complying with Contract requirements. The Owner's approval of a <br /> Submittal did not constitute a waiver of the Contract requirements. The Owner or Owner's <br /> Representative shall respond to a Submittal within ten(10) working days of receipt. The Owner <br /> or Owner's Representative may extend this time for good cause by notifying the Contractor. The <br /> Owner will not be obligated to accept or pay for Work performed by the Contractor that may be <br /> affected by materials, Equipment, or methods of work not submitted in a timely manner so that <br /> final review can be accomplished before the affected Work is complete. The Owner shall not be <br /> responsible for Delays, inefficiencies, or any additional costs or expenses caused in whole or in <br /> part by Contractor's failure to submit required information in sufficient time for review, <br /> comment, and correction. Contractor's failure to submit required information in sufficient time <br /> for review, comment and correction shall be deemed a waiver of any and all Contract Claims for <br /> adjustment of Contract Sum or Contract Time arising out of, or related to, such a Submittal. <br /> Contractor acknowledges and agrees that it may not rely upon receiving the Owner's response to <br /> a Submittal in less than thirty (30) days, unless the Owner explicitly changes this section by a <br /> signed Change Order. Requests for information or clarification from the Contractor to the Owner <br /> shall be treated as a Submittal. <br /> 2.5 Contractor's Copies of Contract Documents <br /> A. The Contractor shall keep at the construction site at least one set of Contract Documents and one <br /> set of full-size Drawings that shall be available to the Owner's Representative and Owner. <br /> i <br /> PSO6 REROUTE 007213 - 13 <br /> WO NO.—UP3583 MAY 2016 <br /> I <br />