1 <br /> POLICE HQ—MASONRY CLEANING AND REPAIR APRIL 15, 2016 <br /> SECTION 01 3216—CONSTRUCTION PROGRESS SCHEDULE <br /> ' PART 1 -GENERAL <br /> 1.01 CONSTRUCTION SCHEDULE <br /> A. The Contractor shall prepare a construction schedule showing all tasks required to perform the work. <br /> Schedule shall show all tasks performed by all trades that is required to perform work within the <br /> contract time. The Schedule shall include sufficient time for cleaning,punch list review and <br /> completion of punch list items prior to the designated physical completion date. <br /> 1.02 FORMAT <br /> A. The Schedule shall be a critical path method Gantt chart style. <br /> B. The Schedule shall clearly identify all work and detailed to show specific steps to perform work. <br /> The relationship between the work items shall show the starting date,length of time required to <br /> perform work, completion of the work within the time frame shown. <br /> C. All work found on the schedule of values shall be clearly identified. Unless otherwise expressly <br /> authorized in writing by the Owner's representative, the Contractor must integrate the schedules with <br /> the Schedule of Values and unit price items so that each construction activity is represented by a <br /> dollar value. <br /> D. Submittals dates shall be included and the relationship between submittal and the work item shall be <br /> identified <br /> E. Materials requiring long lead times shall be clearly identified on the schedule. This shall include: <br /> 1. Date materials musts be ordered <br /> 2. Time for manufacturing <br /> 3. Time for delivery <br /> 4. Delivery date(expected date materials to be at the project) <br /> 5. Date of Installation <br /> 1.03 SUBMITTAL <br /> A. At the pre-construction meeting,a preliminary schedule is required to be submitted. Once the <br /> preliminary schedule has been approved,the schedule shall become the Project Schedule. The <br /> Project Schedule,as approved by the Owner,will be an integral part of the contract and will establish <br /> interim completion dates for the various activities under the contract. <br /> ' B. Schedule shall be submitted electronic. Acceptable format .mmp <br /> C. Review by the Owner or Owner's Representative shall not constitute approval or acceptance of the <br /> Contractor's construction means,methods, sequencing,logic,order,precedence and succession of <br /> activities or Contractor's ability to complete the Work in a timely manner. <br /> D. The review/approval of any schedule shall not transfer any of the Contractor's responsibilities to the <br /> Owner. <br /> CONSTRUCTION PROGRESS SCHEDULE 01 3216 - 1 <br /> I <br />