CITY OF EVERETT SPECIAL PROVISIONS <br /> 3. Determining the gross amount of potential additional compensation for Home I <br /> Office Overhead due to the project extension. This is accomplished by <br /> multiplying the Daily Rate of Allocable Overhead by the number of days of <br /> project extension caused solely by the City. This results in the Gross Amount of <br /> Additional Home Office Overhead Compensation. <br /> 4. Adjusting the Gross Amount of Additional Home Office Overhead Compensation <br /> for any additional contribution for Overhead received by the Contractor on any <br /> Change Orders that are being presented and resolved concurrently with the <br /> subject calculation for Unabsorbed and/or Extended Home Office Overhead. <br /> The necessary adjustment would be to reduce the Gross Amount of Additional <br /> Home Office Overhead Compensation by any additional compensation for111 <br /> Overhead included in any direct cost claims being resolved concurrently with <br /> any claim for Extended and/or Unabsorbed Home Office Overhead. <br /> Contractor shall not receive compensation for cost of use of equity capital. I <br /> 1-09.5 Deleted or Terminated Work <br /> Delete the first paragraph, beginning with "The Engineer may delete", and the second <br /> paragraph, beginning with "Payment for completed items", and substitute the following: <br /> The City's Representative may delete Work as provided in 1-04.4 CHANGES or may <br /> terminate the Contract in whole or part as provided in 1-08.10(2) TERMINATION FOR <br /> PUBLIC CONVENIENCE. When the Contract is partially terminated for the City's <br /> convenience, the partial termination shall be treated as a deductive Change Order for <br /> payment purposes under this section. <br /> Payment for completed items will be at contract unit prices or pursuant to the Schedule <br /> of Values. <br /> Delete the fourth paragraph, beginning with "Contract Time", and the fifth paragraph, <br /> beginning with "Acceptable Materials", and substitute the following: <br /> Acceptable materials ordered by the Contractor prior to the date the Work was <br /> terminated or deleted will either be purchased from the Contractor by the City at the <br /> actual cost and shall become the property of the City, or the City will reimburse the <br /> Contractor for the actual costs of returning these materials to the suppliers. <br /> If Contractor disagrees with the adjustment of Contract Sum determined by the City's <br /> Representative, Contractor may submit a Contract Claim for the difference between <br /> the amount determined by the City's Representative and the amount sought by the <br /> Contractor. <br /> Contractor shall not be entitled to any anticipated profits on deleted, terminated, or <br /> uncompleted Work will be allowed. <br /> 1-09.6 Force Account <br /> Supplement 1-09.6 by adding the following: I <br /> The City has estimated and included in the Proposal, dollar amounts for all items to be <br /> paid per Force Account, only to provide a common Bid for Bidders. All such dollar <br /> amounts are to become a part of Contractor's total bid. However, the City does not <br /> warrant expressly or by implication that the actual amount of Work will correspond with <br /> those estimates. Payment will be made on the basis of the amount of Work actually <br /> authorized by Engineer. <br /> 1-09.9 Payments <br /> Delete 1-09.9 and substitute the following: <br /> Water Main Replacement"Q" Division 1 —GENERAL CONDITIONS July 8, 2016 <br /> -Broadway <br /> WO No.—UP3612 SP-106 <br /> 1 <br />