My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Marshbank Construction 5/9/2016
>
Contracts
>
Capital Contract
>
Marshbank Construction 5/9/2016
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
5/4/2018 9:23:23 AM
Creation date
5/20/2016 10:28:35 AM
Metadata
Fields
Template:
Contracts
Contractor's Name
Marshbank Construction
Approval Date
5/9/2016
Council Approval Date
4/16/2016
Department
Public Works
Department Project Manager
Ryan Sass
Subject / Project Title
41st St to W Marine View Dr Corridor Imprvts
Public Works WO Number
PW 3472
Tracking Number
0000049
Total Compensation
$2,758,753.00
Contract Type
Capital Contract
Retention Period
10 Years Then Transfer to State Archivist
Document Relationships
Marshbank Construction 1/25/2017 Change Order 1
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
MARSHBANK CONSTRUCTION 3/26/2018 Change Order 3
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
Marshbank Construction 6/26/2017 Change Order 2
(Contract)
Path:
\Documents\City Clerk\Contracts\Capital Contract
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
428
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
I <br /> I <br /> 1 Contaminated Soil and Hazardous Material <br /> 2 The Engineer will determine the limits of excavation required. All material that is <br /> 3 designated by the Engineer to be removed shall be handled and stored in a manner 111 <br /> 4 that prevents the spread of contamination to adjacent soil or water. Separate stockpiles <br /> 5 shall be maintained for known hazardous or contaminated material and for suspected I 6 hazardous or contaminated material. The Contractor shall transport hazardous or <br /> 7 contaminated material and dispose of it at a permitted facility. The Contractor shall <br /> 8 provide the Engineer with a copy of the shipping manifest or bill of lading indicating the <br /> I <br /> 9 amount of material hauled to disposal, and bearing the disposal site operator's <br /> 10 confirmation for receipt of the material. <br /> 11 <br /> 12 Contaminated Water <br /> I <br /> 13 All water that is removed from the areas of contamination, including free water that <br /> 14 leaches from contaminated soil stockpiles or water that is suspected of being <br /> 15 contaminated, shall be collected, handled and stored in a manner that prevents the <br /> 16 spread of contamination to adjacent soil or water. The Contractor shall transport <br /> 17 contaminated water and dispose of it at a permitted facility. The Contractor shall <br /> 18 provide the Engineer with a copy of the shipping manifest or bill of lading indicating the <br /> I <br /> 19 amount of material hauled to disposal, and bearing the disposal site operator's <br /> 20 confirmation for receipt of the material. <br /> 21 I 22 2 o2 4�G 2 <br /> 23 Measurement <br /> 24 <br /> 25 2`02541xf ST1 ,GR2 <br /> 26 Section 2-02.4 is supplemented with the following: <br /> 27 <br /> 28 E202.40 4 2 <br /> 29 (December 4, 2006) <br /> 30 Hazardous material excavation including haul will be measured by the cubic yard. All <br /> 31 excavated material will be measured in the position it occupied before the excavation <br /> 32 was performed. An original ground measurement will be taken using cross-section or <br /> 33 digital terrain modeling survey techniques. The original ground will be compared with a <br /> I <br /> 34 survey of the excavation area taken after the work is completed. <br /> 35 <br /> 36 2025GR <br /> 37 Payment <br /> 38 <br /> 39 �2 2.S.I1STGR2 <br /> 40 Section 2-02.5 is supplemented with the following: <br /> 41 <br /> 42 2 02.5 `QPT .G'' <br /> 43 (December 4, 2006) <br /> 44 "Hazardous Material Handling And Disposal", by force account as provided in Section 1- <br /> 45 09.6. <br /> 46 <br /> 47 All costs associated with storing stockpiled hazardous waste and contaminated soils, <br /> 48 collecting, handling and storing contaminated water, loading the stockpiled material into <br /> 49 the hauling conveyance for transport to the disposal site, and transporting and <br /> 41st STREET TO WMVD FREIGHT <br /> CORRIDOR IMPROVEMENTS <br /> FED AID#STPUL-9931(012); PW#3472 SP-78 February 10,2016 <br />
The URL can be used to link to this page
Your browser does not support the video tag.