|
Washington State Department of Transportation Page 2 Six-year Transportation Improvement Program
<br /> Agency Everett
<br /> From 2005 to 2010
<br /> County No. 31 Hearing Date
<br /> City No. 420 Adoption Date
<br /> MPO PSRC Resolution No.
<br /> Project Identification Project Costs in Thousands of Dollars Federally Funded
<br /> A. Federal Aid No. Fund Source Information Expenditure Schedule Projects Only
<br /> B. Bridge No. Federal Funding Local Agency
<br /> C. Project Title -'
<br /> RNV
<br /> D. StreeVCounty Road Name or Number Improve- Phase Federal Federal State 4th Required
<br /> Functional Priority E. Beginning MP or road-Ending MP or road merit Total Utility Project Start Fund Cost by Fund State Local Total 1st 2nd 3rd thru Envir. Date
<br /> Class Number F. Describe Work to be Done Type Status Length Codes Phase (mMdd/yy) Code Phase Code Funds Funds Funds (2005) (2006) (2007) 6th Type (MM/YY)
<br /> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
<br /> 11 8 3 phases in project 3 P 0.3 r 0 PE 1/1/2009 WSDOT 3,000 1,000 4,000 4,000 •
<br /> Interstate RW 6/1/2010 WSDOT 1,500 500 2,000 2,000 11/1/2011
<br /> 15/East Marine View Dr. Frwy.Interchange CN 6/12012 WSDOT 17,000 7,000 24,000
<br /> 1-5 at East Marine View Drive FMSIB 5,000 5,000
<br /> 1-5 t E.Marine View Dr.
<br /> Add on and off-ramp to and from the north Totals 26,500 8,500 35,000 6,000
<br /> 14 9 3 phases in project 3 P 0.3 0 PE 6/1/2009 RTID 30,000 30,000 8,000
<br /> Freeways 5/640 RW 6/1/2010 RTID 50,000 50,000 EIS 3/12012
<br /> US 2 Improvements CN 6/1/2012 RTID 243,000 243,000
<br /> US 2 Improvements
<br /> 15 and SR 204
<br /> Add lane each direction,improve interchanges Totals 323,000 323,000 8,000
<br /> 12 8 3 phases in project 3 P 0.3 0 PE 1/1/2009 WSDOT 4,000 4,000 4,000
<br /> Freeways RW 6/1/2010 WSDOT 11,000 11,000 5,000 EIS 3/1/2012
<br /> SR 526/Hardeson Road Interchange CN 6/1/2012 WSDOT 23,000 23,000
<br /> SR 526
<br /> SR 526 at Hardeson Road
<br /> Add on and off-ramps Totals 38,000 0 38,000 9,000
<br /> 14 1 3 phases in project 4 S 1.5 C PE 3/1/1994 WSDOT 140 3,379 3,519
<br /> Principal P RW 7/1/1998 5,045 5,045
<br /> Arterial 19th Avenue SE(SR 527)Improvements T CN 6/1/2004 WSDOT 20,000 20,000 14,530
<br /> 19th Avenue SE(SR 527) 0
<br /> 112th Street SE to 132nd Street 5E
<br /> Design and construct addit.lanes,signal improv.,etc. Totals 20,140 8,424 28,564 14,530
<br /> 14 2 HP-1998(021) 4 phases in project 4 S,P 1.5 C PE 3/1/2003 DEMO 500 468 968 200
<br /> Principal P PE FAST 600 600
<br /> Arterial East Marine View Drive Improvements T RW 9/1/2005 DEMO 592 592 500
<br /> East Marine View Drive O CN 7/1/2006 DEMO 3,808 FMSIB 600 859 5,267 7300
<br /> North Broadway to Interstate 5 DEMO 3,000 3,000
<br /> Design,construct roadway widening and improvements Totals 8,500 600 1,327 10,427 700 7,300
<br /> 14 3 2 phases In project 3 S 0.2 C PE 10/1/2004 TIA 45 22 67
<br /> Principal P CN 6/1/2005 TIA 455 228 683 683 No
<br /> Arterial Broadway/Beverly Blvd.Intersection Improv. T
<br /> So.Broadway, Beverly Boulevard 0
<br /> Broadway at Beverly to SR 526
<br /> Design and construct intersection improvements Totals 500 250 750 683
<br /> 14 4 2 phases in project 4 P 0.3 C PE 1/1/1999 - 75 75
<br /> Principal P CN 7/1/2008 TIA 225 200 425 425
<br /> Arterial Evergreen Way Widening T
<br /> Evergreen Way 0
<br /> 11500 block to Airport Road
<br /> Design,construct street widening/improvements _ Totals 225 275 500 425
<br /> 14 5 3 phases in Project 31 P 0 C PE 2/1/2011 - RTID 4,818 4,818
<br /> Principal P RW 2/1/2012 RTID 1,355 1,355
<br /> Arterial Broadway Corridor Improvements T CN 3/1/2014 RTID 27,853 27,853
<br /> South Broadway Corridor 0
<br /> SR 526 to 41st Street
<br /> Widen to 5 lanes with bike lanes&sidewalks Totals 34,0261 34,028 0
<br />
|